Force Majeure and Rising Construction Costs Australia | Blaze Business & Legal

What this article covers

Force majeure is one of the first things contractors ask about when input costs rise sharply. In most cases, the honest answer is that it will not help. This article explains why, sets out the narrow circumstances where it might, and points to the realistic alternatives.

What force majeure means in construction contracts

Force majeure is a contract clause that excuses a party from performing their obligations, or grants additional time to perform, when performance is prevented or delayed by an event outside that party’s reasonable control that could not reasonably have been anticipated or guarded against.

The clause is not implied by Australian law. It exists only if it is written into the contract. Its scope is limited to what the clause specifically says.

In Australian construction contracts, force majeure events are typically defined by a list or by a general description with specific inclusions: acts of God, war, terrorism, riots, pandemic, government action, and natural disasters.

Why fuel price increases are unlikely to qualify as force majeure

Price increases are not physical prevention. Force majeure clauses are designed to address situations where a party is physically prevented from performing. A contractor who cannot get materials because a port is closed has a force majeure argument. A contractor who can get materials but at a higher price does not. Courts and arbitrators consistently distinguish between impossibility of performance and increased cost of performance.

Fuel price volatility is foreseeable. Force majeure clauses generally require the event to be unforeseeable at the time of contracting. Fuel price volatility is a well-known commercial risk in construction. It is the reason rise and fall clauses exist. A court is unlikely to accept that a contractor tendering in 2024 could not have foreseen that fuel prices might change during project delivery.

Blaze Business & Legal

Need advice on your specific position?

Three fixed-fee services covering your legal, cost, and business situation. Rachelle Hare and Shannon Drew directly.

When force majeure might be relevant

Force majeure is not irrelevant to the 2026 cost environment. Specific scenarios worth examining: a government-imposed import restriction on a specific material your contract relies on; a natural disaster that physically disrupts your supply chain; a sanctions event preventing access to materials from a previously contracted supplier.

In each of these cases, the argument is about supply disruption, not price. That is a materially different claim.

What force majeure typically provides even when it applies

Even where a force majeure event is established, the remedy in most Australian construction contracts is time, not money. The contractor gets an extension of time. They do not automatically receive additional cost.

What to do if your force majeure claim has been rejected

Submitting a force majeure claim that gets rejected does not prevent you from pursuing variation claims or other contract rights, provided you do not take steps that are inconsistent with those claims. Get legal advice before taking any further steps after a rejection.

Your realistic options

Rise and fall clauses

The complete 8-step system

Integrated legal and business advisory

FAQ

Does force majeure cover fuel price increases in Australian construction contracts?
In most cases, no. Force majeure addresses situations where performance is physically prevented, not simply more expensive. Courts consistently distinguish between impossibility of performance and increased cost of performance.
Is fuel price volatility considered a foreseeable event?
Yes. Fuel price volatility is a well-known commercial risk in construction and is the reason rise and fall clauses exist. A court is unlikely to accept that a contractor tendering in 2024 could not have foreseen that fuel prices might change during project delivery.
What does force majeure actually provide even when it applies?
In most Australian construction contracts, the remedy is time, not money. The contractor gets an extension of time. They do not automatically receive additional cost.
If my force majeure claim is rejected, do I still have other options?
Yes. Submitting a force majeure claim that gets rejected does not prevent you from pursuing variation claims or other contract rights. Get legal advice before taking further steps. Read about your other options.

Blaze Business & Legal

Get Help with Your Contracts, Cost Position, and Business

Three fixed-fee services for construction businesses working through the cost crisis. Rachelle Hare and Shannon Drew directly, from the first conversation.

Strategy Session $750 + GST Contract Audit $1,500 + GST Business Triage $1,975 + GST
25+ years in construction. Fixed fees. No junior staff.
Rachelle Hare, Managing Director, Blaze Business and Legal
Rachelle Hare
Managing Director and Principal, Blaze Business & Legal

Rachelle Hare is a construction lawyer and business adviser with 25 years of experience, including in-house roles at Thiess, Laing O’Rourke, Acciona, DHA, and UGL. She advises construction businesses on contracts, cost recovery, risk, procurement, commercial strategy, and business structuring across Queensland and Australia.