Rise and Fall Clauses in Construction Contracts Australia | Blaze Business & Legal

What is a rise and fall clause

A rise and fall clause is a contract provision that adjusts the contract price when the cost of specified inputs changes after the date of tender. The clause identifies which inputs are covered, sets a base index or base price, and provides a formula for calculating the adjustment when costs move relative to that base.

The purpose of the clause is to allocate cost fluctuation risk between the principal and the contractor. Without one, the contractor carries all cost risk. With one, some or all of that risk shifts to the principal.

Rise and fall clauses appear under various names: price escalation clauses, cost adjustment clauses, CPI adjustment clauses, or fluctuation clauses.

Do most Australian construction contracts have rise and fall clauses?

No. The majority of private sector construction contracts in Australia are fixed-price lump-sum contracts with no cost adjustment mechanism. Rise and fall clauses are more common in government contracts, long-duration infrastructure contracts, and contracts involving significant materials procurement.

If you do not know whether your contract has a rise and fall clause, check the full contract document including all schedules and annexures. Search for: rise and fall, price adjustment, cost adjustment, escalation, fluctuation, CPI adjustment, index adjustment. The clause will not be implied. If it is not written in, it does not exist.

How to find the clause in your contract

AS 4000: check Special Conditions carefully. No automatic mechanism exists in the standard General Conditions.

AS 4300: same search applies. Check Schedule 1 and any Special Conditions.

NEC4: Option X1 is the price adjustment for inflation option. Check whether Option X1 is listed in the Contract Data as a selected option. If it is not listed, it does not apply.

GC21 Edition 2 (NSW Government): Schedule 7 deals with cost reimbursement. Check whether Schedule 7 has been completed in the Contract Particulars.

AS 2124: check Special Conditions and any Schedule provisions.

How rise and fall clauses work in practice

The clause selects one or more published indices as the reference point. Common indices include the ABS Producer Price Index, the ABS Consumer Price Index, or a project-specific materials index.

The clause sets a base date, usually the date of tender or contract execution. At each payment milestone, the current index value is compared to the base value. If the current value is higher, the contractor is entitled to a price adjustment.

The clause typically specifies which portions of the contract value are subject to adjustment. A clause that applies to 40 per cent of the contract value provides 40 per cent of the protection, not full protection.

Common problems

The base index does not match actual cost increases. A clause that adjusts on CPI will not accurately reflect a 67 per cent diesel increase.

The clause was not included in back-to-back subcontracts. If your head contract has a rise and fall clause but your subcontracts do not, the protection does not flow through.

Notice obligations have not been met. Many clauses require notice of a claim within a specified period. Missing the deadline can extinguish the entitlement.

Notice obligations

Blaze Business & Legal

Need advice on your specific position?

Three fixed-fee services covering your legal, cost, and business situation. Rachelle Hare and Shannon Drew directly.

What to do if your contract does not have a rise and fall clause

The absence of a rise and fall clause does not mean there are no options. It means the options require more effort, more documentation, and in most cases a commercial negotiation rather than a straightforward contract claim.

Your options when there is no cost protection clause

The complete 8-step response system

Shannon Drew’s full project cost analysis

Get integrated legal and business advisory

FAQ

Does every Australian construction contract have a rise and fall clause?
No. Most private sector construction contracts are fixed-price lump-sum contracts with no cost adjustment mechanism. Rise and fall clauses are more common in government contracts and long-duration infrastructure projects.
Where do I look for a rise and fall clause in my contract?
Check the Special Conditions carefully. Rise and fall mechanisms are frequently added by special condition rather than appearing in the standard General Conditions. Also check all schedules and annexures.
What happens if I miss the notice deadline for a rise and fall claim?
Missing the deadline can extinguish the entitlement entirely under many contracts. Read more about notice obligations.
My rise and fall clause adjusts on CPI. Will that cover a 67% diesel increase?
No. CPI is a broad consumer price measure. A 67% diesel increase will significantly outpace CPI movements. The clause will provide partial protection, not full recovery.

Blaze Business & Legal

Get Help with Your Contracts, Cost Position, and Business

Three fixed-fee services for construction businesses working through the cost crisis. Rachelle Hare and Shannon Drew directly, from the first conversation.

Strategy Session $750 + GST Contract Audit $1,500 + GST Business Triage $1,975 + GST
25+ years in construction. Fixed fees. No junior staff.
Rachelle Hare, Managing Director, Blaze Business and Legal
Rachelle Hare
Managing Director and Principal, Blaze Business & Legal

Rachelle Hare is a construction lawyer and business adviser with 25 years of experience, including in-house roles at Thiess, Laing O’Rourke, Acciona, DHA, and UGL. She advises construction businesses on contracts, cost recovery, risk, procurement, commercial strategy, and business structuring across Queensland and Australia.