Fixed Price Contract Cost Increases: Your Options | Blaze Business & Legal

The starting point: most contractors are here

The majority of Australian construction businesses dealing with fuel and input cost increases in 2026 are working under fixed-price lump-sum contracts with no rise and fall clause. Being in this position does not mean there are no options. It means the options require more effort, more documentation, and in most cases a commercial negotiation rather than a straightforward contract claim.

Option 1: negotiate a commercial variation

The most practical path for most contractors is a direct commercial negotiation with the principal. This is not a legal claim. It is a business conversation. The contractor approaches the principal with a documented case showing the actual cost impact and proposes a mechanism for sharing that impact.

This works more often than contractors expect. The principal has a project to deliver. A contractor absorbing unrecoverable losses becomes a program risk. Subcontractors doing the same become an insolvency risk on the supply chain.

The commercial variation needs to be executed as a deed of amendment, signed by both parties.

What your principal is thinking

Option 2: examine your contract for variation entitlements you may have missed

Many contractors conclude they have no contractual entitlement without having done a thorough review of the whole contract. Check carefully:

Special conditions that modify the standard form — these frequently add cost adjustment mechanisms that the standard General Conditions do not include.

Superintendent-directed variations — if the Superintendent has directed you to use a specific material, method, or programme that increased your costs, that direction may be a compensable variation regardless of whether the contract has a rise and fall clause.

Delays caused by the principal — if the principal caused delays that extended the project into a higher-cost period, the principal may be liable for those delay costs.

Rise and fall clauses explained

Blaze Business & Legal

Need advice on your specific position?

Three fixed-fee services covering your legal, cost, and business situation. Rachelle Hare and Shannon Drew directly.

Option 3: contract frustration

Frustration is a common law doctrine that applies where an event outside the parties’ control makes performance of the contract radically different from what was contemplated. Courts apply the doctrine strictly and are reluctant to find frustration where the contract could still be performed, even at a materially higher cost.

Option 4: unconscionable conduct

The Australian Consumer Law prohibits unconscionable conduct in trade or commerce. In limited circumstances, a principal’s insistence on strict performance in circumstances where the contractor would suffer extreme hardship, and where the principal knew about that hardship and took advantage of it, may constitute unconscionable conduct. This is a high bar.

What all of these options have in common

All require a clear, documented picture of your actual cost position across all six inputs, including overhead recovery and pricing exposure. You cannot negotiate a commercial variation without knowing what you are negotiating for.

Shannon Drew’s full project cost analysis

The complete 8-step system

Integrated legal and business advisory

FAQ

Can I ever recover cost increases on a fixed-price contract with no rise and fall clause?
Sometimes yes. The most realistic path is a commercial variation negotiated with the principal. Also check whether a Superintendent-directed change increased your costs, as that may give rise to a variation claim regardless of the rise and fall position.
What is the difference between force majeure and contract frustration?
Force majeure is a contractual mechanism that must be written into the contract. Frustration is a common law doctrine that applies where an event makes performance radically different from what was contemplated. Both are difficult to establish for cost increases. Read more about force majeure.
What documentation do I need to support a commercial variation claim?
A documented analysis of your actual cost impact across all six inputs, specific to your project, including overhead recovery and pricing exposure. Shannon Drew provides this analysis in a form suitable for use in negotiations with a principal or their quantity surveyor.
How do I approach my principal about a cost variation?
Frame it as a delivery and project risk issue, not contractor hardship. Come with a specific dollar number, a specific mechanism, and documented evidence. Read about what your principal is thinking.

Blaze Business & Legal

Get Help with Your Contracts, Cost Position, and Business

Three fixed-fee services for construction businesses working through the cost crisis. Rachelle Hare and Shannon Drew directly, from the first conversation.

Strategy Session $750 + GST Contract Audit $1,500 + GST Business Triage $1,975 + GST
25+ years in construction. Fixed fees. No junior staff.
Rachelle Hare, Managing Director, Blaze Business and Legal
Rachelle Hare
Managing Director and Principal, Blaze Business & Legal

Rachelle Hare is a construction lawyer and business adviser with 25 years of experience, including in-house roles at Thiess, Laing O’Rourke, Acciona, DHA, and UGL. She advises construction businesses on contracts, cost recovery, risk, procurement, commercial strategy, and business structuring across Queensland and Australia.