Extension of Time (EOT) in construction contracts refers to a contractual entitlement allowing a Contractor additional time to achieve Practical Completion where delay events occur beyond the Contractor’s control. A properly prepared EOT protects the Contractor from exposure to Liquidated Damages and preserves commercial position when delay affects the critical path of the project.
Introduction
In the Construction Industry, meeting milestones and achieving Practical Completion by the Date for Practical Completion is often easier said than done.
Weather, regulatory changes, unforeseen site conditions, variations, supply disruption or actions of the Principal can interrupt progress. When that happens, exposure to Liquidated Damages becomes a real commercial issue.
Extension of Time clauses sit at the centre of that risk allocation. Whether additional time is available, and how it is claimed, depends entirely on the wording of the Construction Contract.
What is an Extension of Time?
An Extension of Time, commonly referred to as an EOT, is a contractual mechanism allowing the Contractor additional time to achieve Practical Completion where delay events occur.
EOTs are usually not automatically granted, but must be claimed by the Contractor in accordance with the terms of the contract.
Different contracts contain different notice periods, evidentiary thresholds and approaches to concurrent delay. Some contracts are relatively balanced. Others are tightly drafted and procedural. Contractors need to understand what their particular contract requires before responding to delay.
Typical delay events that may give rise to an EOT include:
Adverse weather beyond contractual allowances
Variations or design changes
Latent conditions
Delays caused by the Principal
Regulatory approval delays
Labour or material shortages, where permitted under the contract
Entitlement turns on the clause wording and the impact on the critical path of the program.
Why Extension of Time Clauses Matter Commercially
Extension of Time clauses are among the most commercially significant provisions in construction contracts.
Without EOT protection, Contractors can become exposed to Liquidated Damages for delay events outside their control. In practice, many disputes arise not because there was no entitlement, but because notice was incomplete, late or unsupported by sufficient evidence.
EOT administration affects cashflow, margin and dispute risk. Poorly handled delay claims often sit behind larger commercial problems later in the project lifecycle.
Courts and tribunals have considered:
Time bar enforceability
Concurrent delay
Ownership of float
Prolongation claims
Superintendent assessment obligations
Understanding how these issues operate in your contract makes a material difference to commercial outcomes for your construction business.
Common Delay Scenarios
Construction projects encounter delay for many reasons. Whether an EOT is available depends on contract wording and evidence.
4.1 Adverse Weather
Unusual or prolonged weather events can halt work and affect sequencing.
4.2 Variations and Design Changes
Changes to scope often disrupt procurement, resourcing and sequencing, particularly where they affect critical activities.
4.3 Latent Conditions
Unexpected ground conditions or inaccurate site data can cause significant delay.
4.4 Regulatory and Approval Delays
Where permits or approvals sit outside the Contractor’s control, delay entitlement may arise.
4.5 Supply and Labour Disruption
Shortages can affect productivity and sequencing, although entitlement depends heavily on the contract.
In each case, causation and program impact are central.
Time Bars and Notice Risk
Many contracts include strict notice requirements for EOT claims.
A time bar clause requires the Contractor to notify the Principal or Superintendent within a defined timeframe after becoming aware of a delay event. If that timeframe is missed, entitlement may be reduced or lost entirely.
The consequence of non-compliance can be significant. Even where a delay is legitimate, failure to comply with notice provisions may leave the Contractor exposed to Liquidated Damages and without time relief.
In some circumstances, arguments about prevention, estoppel or quantum meruit may arise. However, those arguments are uncertain and fact-specific. Relying on them after the event is rarely ideal.
Early identification of delay events and structured notice processes significantly reduce this risk.
Are Extension of Time Clauses Important?
Extensions of Time are one of the more important clauses in construction contracts. They help maintain fairness and equity between the contracting parties, ensuring that the Contractor is not held responsible for delays beyond its control. This includes delays caused by the Principal which contractually entitle the Contractor to an EOT.
EOT provisions allow for a practical adjustment of the project schedule, timeline and milestones to accommodate unexpected challenges. This ensures that construction projects can proceed smoothly while the Contractor addresses unforeseen obstacles.
A whole body of case law on extension of time has arisen, covering the interpretation of EOT provisions in construction contracts, how extension of time provisions should be drafted, extension of time claims, the rights of a Contractor to be granted an extension of time, extension of time claim methods, ownership of the float, prolongation claims, and so on. It’s critical for all Contractors to have staff who are skilled in Contract Management and administering Extension of Time Claims. If you don’t have those skillsets in-house, you can engage them internally – give Rachelle Hare a call to discuss how she can help your business optimise its contracting and increase its success rates for Extension of Time claims.
Why Do You Need Extensions of Time?
Construction projects encounter delays for a multitude of reasons, making EOTs very important for Contractors. Otherwise, they would go broke while trying to meet schedules that have been delayed through no fault of the Contractor.
Here are some common scenarios where EOTs are necessary:
1. Bad Weather: Severe weather events like storms or heavy rainfall can halt construction work, and predicting such events accurately is challenging. These weather-related delays can significantly disrupt project schedules and are not something within the control of the Contractor, even if they are allowed to build in a float / allowance for a certain number of days of delay before claiming an EOT.
2. Design Changes: During a project, project plans and design of the Works may evolve due to updated specifications, client preferences for alterations or unexpected site conditions. These changes usually force the Contractor to carry out additional work and, consequently, require more time to be spent by the Contractor to bring the Works to completion.
3. Surprise Site Issues: Unforeseen complications underground, such as unstable ground, different soil composition, errors in the geotechnical report, or the discovery of hidden artifacts, demand extra time and effort to address, and the Contractor should be entitled to claim an EOT.
4. Red Tape and Rules: Navigating the bureaucratic maze of permits and approvals can lead to delays, as these permissions are often prerequisites for specific project tasks.
5. Shortages: Shortages of skilled labour or essential materials, whether due to high demand or unforeseen events, can result in significant project setbacks.

Keeping Good Records
To request an EOT, meticulous record-keeping is essential. Here’s what you should document:
1. Daily Reports: Maintain daily records detailing on-site activities, weather conditions, work progress, and any encountered issues. This chronology helps establish the timeline of delays.
2. Messages and Meetings: Archive all correspondence, including emails, letters, and meeting notes, that discuss delays and EOT requests. This documentation serves as evidence of communication regarding delays.
3. Change Orders: If project plans change, document these alterations. This documentation substantiates the need for additional time due to modifications in the scope of work.
4. Photos and Videos: Take photographs and videos at various project stages. These visuals provide tangible evidence of delays attributed to factors like adverse weather, site issues, or design changes. Properly label and organize these visual records to support EOT claims.
Terms of your Construction Contract
Construction contracts outline specific procedures for requesting EOTs. Adhering to these rules is imperative to ensure that your request is valid:
1. Notice: Notify the project owner or relevant parties as soon as you anticipate potential delays. Contracts typically specify deadlines and methods for providing this notice.
2. Timing: Contracts set specific deadlines for submitting EOT requests. Missing these deadlines can jeopardize your chances of obtaining an extension.
3. Evaluation: The contract outlines the criteria for determining whether an extension is warranted. Factors considered include the cause of the delay and its impact on the project schedule.
4. Multiple Delays: In cases where multiple delays occur concurrently, contracts define responsibility and the appropriate course of action.

The Contract Manager’s Role
The Contract Manager plays a pivotal role in the EOT process. Their responsibilities include:
1. Expertise: Contract administrators must possess a comprehensive understanding of construction processes, project management, and contract terms. They are impartial and do not take sides.
2. Communication: They serve as intermediaries between contractors and project owners, gathering information and ensuring clear communication to prevent misunderstandings.
3. Decision-Making: Contract administrators base their decisions on contract terms, relying on facts and documents to explain their determinations. Fair and transparent decision-making is essential to maintain satisfaction among all parties involved.
Extensions of Time and Liquidated Damages
Liquidated damages represent a pre-agreed estimate of the loss the Principal may suffer if the project runs behind schedule and the Contractor does not achieve Practical Completion by the Date for Practical Completion.
Extensions of Time (EOTs) and liquidated damages are closely intertwined, and the following aspects should be considered:
1. Time Analysis: A thorough examination of delays and their impact on the project schedule is conducted to determine whether an extension is justified and whether the project owner can claim damages.
2. Concurrent Delays: When both the contractor and external factors contribute to delays, responsibility is assessed, and the necessary extension is granted.
3. No-Fault Extensions: Some contracts allow contractors to request additional time without incurring penalties for delays beyond their control, such as adverse weather.
4. Financial Considerations: Contractual agreements specify the daily rate at which project owners can claim damages. This rate should be a reasonable estimate rather than a punitive measure. When an extension is granted, contractors are exempt from paying damages for that period.
5. Problem Resolution: Both parties must actively work to resolve issues and minimise delays. Project owners should promptly inform contractors of delays and offer assistance, while contractors should take measures to mitigate delays and reduce damages.

Read our Essential Guide to Construction Law
Conclusion
An Extension of Time Clause is an integral component of a Construction Contracts. Maintaining meticulous records, following contractual guidelines, and ensuring fair decisions by contract administrators are essential practices. Balancing the allocation of extra time with financial penalties fosters fairness among all stakeholders in construction projects.
Here are some additional things to think about:
1. EOT Overview
Extensions of Time (EOTs) in construction refer to additional periods granted for project completion beyond the initial deadline. They are typically required due to unforeseen circumstances beyond the contractor’s control.
2. Granting Conditions for EOTs
EOTs are subject to specific conditions outlined in construction contracts. They are often granted for reasons such as natural disasters, regulatory changes, or material shortages.
3. EOT Request Process
Contractors must follow a well-defined process when requesting EOTs. This process includes substantiating the cause of the delay and presenting a revised project completion plan.
4. Typical Delay Causes for which an EOT may be claimed
Common causes leading to EOT requests include adverse weather conditions, project scope changes, material and labor shortages, design issues, and delays in obtaining permits or approvals. In all cases, the terms of the construction contract will govern whether (and when) the Contractor may claim an EOT.
5. Implications of EOT Denial
If an EOT is not granted, contractors may face penalties, such as liquidated damages or legal action for breach of contract.
6. Disputing EOT Notifications
Principals have the option to challenge EOTs if they consider the extension unreasonable, not covered by the contract, or within the contractor’s control. Contractors must provide robust evidence to support their EOT claims.
7. EOT Request Procedures
Contractors should provide written notice to the owner or their representatives, explaining the reasons for the delay and the additional time required, in accordance with contract stipulations.
8. Evidence of External Factors
Contractors must present written evidence demonstrating that external factors were responsible for the delay, rather than issues related to their performance.
9. Contractual and Legal Considerations
Contractors must be well-versed in their contractual rights and obligations regarding EOTs to avoid legal disputes.
10. Rights of Contractors for EOT
Contractors can usually claim/request EOTs for delays outside their control, such as material delivery delays, owner-requested variations, extreme weather, or project disputes.
11. Contractual Clauses and Obligations
Contractors should thoroughly understand the contract’s clauses regarding time extensions, including any limits and notice requirements, to avoid future.
Common Delay Scenarios
Construction projects encounter delay for many reasons. Whether an EOT is available depends on contract wording, whether the delay event is allowed by the contract and the evidence the contractor can demonstrate to substantiate the delay.
4.1 Adverse Weather
Unusual or prolonged weather events can halt work and affect sequencing.
4.2 Variations and Design Changes
Changes to scope often disrupt procurement, resourcing and sequencing, particularly where they affect critical activities.
4.3 Latent Conditions
Unexpected ground conditions or inaccurate site data can cause significant delay.
4.4 Regulatory and Approval Delays
Where permits or approvals sit outside the Contractor’s control, delay entitlement may arise.
4.5 Supply and Labour Disruption
Shortages can affect productivity and sequencing, although entitlement depends heavily on the contract.
In each case, causation and program impact are central.
Time Bars and Notice Risk
Many contracts include strict notice requirements for EOT claims.
A time bar clause requires the Contractor to notify the Principal or Superintendent within a defined timeframe after becoming aware of a delay event. If that timeframe is missed, entitlement may be reduced or lost entirely.
The consequence of non-compliance can be significant. Even where a delay is legitimate, failure to comply with notice provisions may leave the Contractor exposed to Liquidated Damages and without time relief.
In some circumstances, arguments about prevention, estoppel or quantum meruit may arise. However, those arguments are uncertain and fact-specific. Relying on them after the event is rarely ideal.
Early identification of delay events and structured notice processes significantly reduce this risk.
Are Extension of Time Clauses Important?
Extensions of Time are one of the more important clauses in construction contracts. They help maintain fairness and equity between the contracting parties, ensuring that the Contractor is not held responsible for delays beyond its control. This includes delays caused by the Principal which contractually entitle the Contractor to an EOT.
EOT provisions allow for a practical adjustment of the project schedule, timeline and milestones to accommodate unexpected challenges. This ensures that construction projects can proceed smoothly while the Contractor addresses unforeseen obstacles.

A whole body of case law on extension of time has arisen, covering the interpretation of EOT provisions in construction contracts, how extension of time provisions should be drafted, extension of time claims, the rights of a Contractor to be granted an extension of time, extension of time claim methods, ownership of the float, prolongation claims, and so on. It’s critical for all Contractors to have staff who are skilled in Contract Management and administering Extension of Time Claims. If you don’t have those skillsets in-house, you can engage them internally – give Rachelle Hare a call to discuss how she can help your business optimise its contracting and increase its success rates for Extension of Time claims.
Why Do You Need Extensions of Time?
Construction projects encounter delays for a multitude of reasons, making EOTs very important for Contractors. Otherwise, they would go broke while trying to meet schedules that have been delayed through no fault of the Contractor.
Here are some common scenarios where EOTs are necessary:
1. Bad Weather: Severe weather events like storms or heavy rainfall can halt construction work, and predicting such events accurately is challenging. These weather-related delays can significantly disrupt project schedules and are not something within the control of the Contractor, even if they are allowed to build in a float / allowance for a certain number of days of delay before claiming an EOT.
2. Design Changes: During a project, project plans and design of the Works may evolve due to updated specifications, client preferences for alterations or unexpected site conditions. These changes usually force the Contractor to carry out additional work and, consequently, require more time to be spent by the Contractor to bring the Works to completion.
3. Surprise Site Issues: Unforeseen complications underground, such as unstable ground, different soil composition, errors in the geotechnical report, or the discovery of hidden artifacts, demand extra time and effort to address, and the Contractor should be entitled to claim an EOT.
4. Red Tape and Rules: Navigating the bureaucratic maze of permits and approvals can lead to delays, as these permissions are often prerequisites for specific project tasks.
5. Shortages: Shortages of skilled labour or essential materials, whether due to high demand or unforeseen events, can result in significant project setbacks.

Keeping Good Records
To request an EOT, meticulous record-keeping is essential. Here’s what you should document:
1. Daily Reports: Maintain daily records detailing on-site activities, weather conditions, work progress, and any encountered issues. This chronology helps establish the timeline of delays.
2. Messages and Meetings: Archive all correspondence, including emails, letters, and meeting notes, that discuss delays and EOT requests. This documentation serves as evidence of communication regarding delays.
3. Change Orders: If project plans change, document these alterations. This documentation substantiates the need for additional time due to modifications in the scope of work.
4. Photos and Videos: Take photographs and videos at various project stages. These visuals provide tangible evidence of delays attributed to factors like adverse weather, site issues, or design changes. Properly label and organize these visual records to support EOT claims.
Terms of your Construction Contract
Construction contracts outline specific procedures for requesting EOTs. Adhering to these rules is imperative to ensure that your request is valid:
1. Notice: Notify the project owner or relevant parties as soon as you anticipate potential delays. Contracts typically specify deadlines and methods for providing this notice.
2. Timing: Contracts set specific deadlines for submitting EOT requests. Missing these deadlines can jeopardize your chances of obtaining an extension.
3. Evaluation: The contract outlines the criteria for determining whether an extension is warranted. Factors considered include the cause of the delay and its impact on the project schedule.
4. Multiple Delays: In cases where multiple delays occur concurrently, contracts define responsibility and the appropriate course of action.

The Contract Manager’s Role
The Contract Manager plays a pivotal role in the EOT process. Their responsibilities include:
1. Expertise: Contract administrators must possess a comprehensive understanding of construction processes, project management, and contract terms. They are impartial and do not take sides.
2. Communication: They serve as intermediaries between contractors and project owners, gathering information and ensuring clear communication to prevent misunderstandings.
3. Decision-Making: Contract administrators base their decisions on contract terms, relying on facts and documents to explain their determinations. Fair and transparent decision-making is essential to maintain satisfaction among all parties involved.
Extensions of Time and Liquidated Damages
Liquidated damages represent a pre-agreed estimate of the loss the Principal may suffer if the project runs behind schedule and the Contractor does not achieve Practical Completion by the Date for Practical Completion.
Extensions of Time (EOTs) and liquidated damages are closely intertwined, and the following aspects should be considered:
1. Time Analysis: A thorough examination of delays and their impact on the project schedule is conducted to determine whether an extension is justified and whether the project owner can claim damages.
2. Concurrent Delays: When both the contractor and external factors contribute to delays, responsibility is assessed, and the necessary extension is granted.
3. No-Fault Extensions: Some contracts allow contractors to request additional time without incurring penalties for delays beyond their control, such as adverse weather.
4. Financial Considerations: Contractual agreements specify the daily rate at which project owners can claim damages. This rate should be a reasonable estimate rather than a punitive measure. When an extension is granted, contractors are exempt from paying damages for that period.
5. Problem Resolution: Both parties must actively work to resolve issues and minimise delays. Project owners should promptly inform contractors of delays and offer assistance, while contractors should take measures to mitigate delays and reduce damages.

Read our Essential Guide to Construction Law
Conclusion
An Extension of Time Clause is an integral component of a Construction Contracts. Maintaining meticulous records, following contractual guidelines, and ensuring fair decisions by contract administrators are essential practices. Balancing the allocation of extra time with financial penalties fosters fairness among all stakeholders in construction projects.
Here are some additional things to think about:
1. EOT Overview
Extensions of Time (EOTs) in construction refer to additional periods granted for project completion beyond the initial deadline. They are typically required due to unforeseen circumstances beyond the contractor’s control.
2. Granting Conditions for EOTs
EOTs are subject to specific conditions outlined in construction contracts. They are often granted for reasons such as natural disasters, regulatory changes, or material shortages.
3. EOT Request Process
Contractors must follow a well-defined process when requesting EOTs. This process includes substantiating the cause of the delay and presenting a revised project completion plan.
4. Typical Delay Causes for which an EOT may be claimed
Common causes leading to EOT requests include adverse weather conditions, project scope changes, material and labor shortages, design issues, and delays in obtaining permits or approvals. In all cases, the terms of the construction contract will govern whether (and when) the Contractor may claim an EOT.
5. Implications of EOT Denial
If an EOT is not granted, contractors may face penalties, such as liquidated damages or legal action for breach of contract.
6. Disputing EOT Notifications
Principals have the option to challenge EOTs if they consider the extension unreasonable, not covered by the contract, or within the contractor’s control. Contractors must provide robust evidence to support their EOT claims.
7. EOT Request Procedures
Contractors should provide written notice to the owner or their representatives, explaining the reasons for the delay and the additional time required, in accordance with contract stipulations.
8. Evidence of External Factors
Contractors must present written evidence demonstrating that external factors were responsible for the delay, rather than issues related to their performance.
9. Contractual and Legal Considerations
Contractors must be well-versed in their contractual rights and obligations regarding EOTs to avoid legal disputes.
10. Rights of Contractors for EOT
Contractors can usually claim/request EOTs for delays outside their control, such as material delivery delays, owner-requested variations, extreme weather, or project disputes.
11. Contractual Clauses and Obligations
Contractors should thoroughly understand the contract’s clauses regarding time extensions, including any limits and notice requirements, to avoid future.





