Two Regimes Govern Your Payment Rights
The Contract and the Security of Payment Legislation
Every construction project in Australia operates under two overlapping frameworks: the payment provisions in the contract, and the security of payment legislation in the state where the work is carried out. In Queensland, that legislation is the Building Industry Fairness (Security of Payment) Act 2017 (Qld), commonly known as BIFA, the BIF Act, or the Security of Payment Act. BIFA cannot be contracted out of, and any clause that tries to limit your rights under it is void to that extent.
Construction Contracts determine how work is valued, when payment claims can be submitted, who certifies the amount payable, and what preconditions must be met before payment falls due. BIFA gives you an independent statutory right to a progress payment and a fast-track adjudication process when that payment is disputed or withheld. Lawyers advising construction clients regularly conform contractual payment clauses to mirror the requirements of the Security of Payment Act, so that a single payment claim document can operate under both frameworks simultaneously.
Payment Claims Start the Same Way
Regardless of which regime you are proceeding under, a payment claim starts with the same steps: prepare a document that identifies the work performed, states the amount claimed, and is served on the respondent in accordance with the contract. The critical difference comes at the point of endorsement.
In most Australian jurisdictions, a payment claim that carries the statutory endorsement gives the claimant access to the adjudication process under the relevant Security of Payment Act if payment is disputed. A claim without the endorsement is a contractual claim only. Many contractors include the statutory endorsement on all of their invoices as standard practice, which does not commit them to pursuing the legislation. The endorsement preserves the option. Whether to invoke the statutory process if payment is withheld is a separate decision, made when the dispute arises.
The Endorsement Decision
In Queensland and all equivalent jurisdictions except the Northern Territory, a payment claim must carry the required endorsement under the relevant Act to trigger the statutory regime. Without it, the claim is a contractual claim only and adjudication under BIFA is not available for that particular claim. In practice, many contractors who endorse all invoices under the Security of Payment Act choose not to use the legislation when a dispute arises, accepting late or reduced payment rather than escalate. The endorsement does not determine the outcome. The decision to pursue under BIFA, or to continue seeking a commercial resolution under the contract, remains open until the statutory time limits for adjudication under the Act expire.
For contractors who do not endorse, or who endorse but decide not to pursue under the legislation, the contractual dispute resolution process applies. That process typically involves the Superintendent or Principal's Representative, followed by the formal dispute resolution procedure under the contract, which may include expert determination, arbitration or litigation. Those options are slower and more expensive than BIFA adjudication.
The Jurisdiction-by-Jurisdiction Position
Security of payment legislation, or SOP Act legislation, differs across Australian jurisdictions. The table below sets out the current legislation, whether endorsement is required, and the required endorsement wording. Contractors working across state borders should confirm the current position for any new project.
| Jurisdiction | Legislation | Endorsement Required | Required Endorsement Wording |
|---|---|---|---|
| Queensland | Building Industry Fairness (Security of Payment) Act 2017 (Qld) | Yes | "This is a payment claim made under the Building Industry Fairness (Security of Payment) Act 2017 (Qld)" |
| New South Wales | Building and Construction Industry Security of Payment Act 1999 (NSW) | Yes (contracts from 21 October 2019) | "This is a payment claim made under the Building and Construction Industry Security of Payment Act 1999 (NSW)" |
| Victoria | Building and Construction Industry Security of Payment Act 2002 (Vic), as amended by the Building Legislation Amendment (Fairer Payments on Jobsites and Other Matters) Act 2025 (Vic) (in force April 2026) | Yes | "This is a payment claim under the Building and Construction Industry Security of Payment Act 2002 (Vic)" |
| Western Australia | Building and Construction Industry (Security of Payment) Act 2021 (WA) (contracts from 1 August 2022) | Yes | "This is a payment claim made under the Building and Construction Industry (Security of Payment) Act 2021 (WA)" |
| South Australia | Building and Construction Industry Security of Payment Act 2009 (SA) | Yes | "This is a payment claim made under the Building and Construction Industry Security of Payment Act 2009 (SA)" |
| Tasmania | Building and Construction Industry Security of Payment Act 2009 (Tas) | Yes | "This is a payment claim made under the Building and Construction Industry Security of Payment Act 2009 (Tas)" |
| ACT | Building and Construction Industry (Security of Payment) Act 2009 (ACT) as amended March 2024 | Yes | "This is a payment claim made under the Building and Construction Industry (Security of Payment) Act 2009 (ACT)" |
| Northern Territory | Construction Contracts (Security of Payments) Act 2004 (NT) | No. The Act applies by implication where the contract is silent on payment terms. Either party can initiate adjudication. | No endorsement required |
For WA contracts entered into before 1 August 2022, the Construction Contracts Act 2004 (WA) continues to apply and operates more closely to the NT model, with statutory adjudication available for contractual payment disputes without a requirement for endorsement.
How Payment Works Under the Contract
Pricing Models and What They Mean for Each Claim
The payment mechanism in a construction contract is shaped first by the pricing model the contract uses. The pricing model determines how the value of completed work is assessed and what the Contractor must demonstrate to support each progress claim.
Lump Sum
A fixed price for a defined scope of work. Progress payments are the proportion of the contract price attributable to work completed during the claim period. The Contractor bears cost overrun risk and retains any benefit from completing work efficiently.
Precise scope definition at contract stage is essential because anything outside it must be separately instructed and valued as a variation.
Schedule of Rates
Payment for the measured quantity of work at agreed rates per item. Progress claims require measurement of quantities delivered during the claim period. Common on civil and infrastructure projects where the full scope cannot be precisely defined at tender.
The risk of quantity variation generally sits with the Principal rather than the Contractor.
Bill of Quantities
Similar to schedule of rates, but every measured item is set out in a structured bill priced at tender. Quantities are re-measured against the bill items and the Contractor is paid for the re-measured quantities at the bill rates.
Discrepancies between bill quantities and actual site quantities, and work not readily billable to any line item, are common sources of payment disputes.
Cost Reimbursable
The Contractor is paid for actual costs incurred plus an agreed fee or margin. Progress claims must be supported by cost records, invoices and timesheets. Open book requirements typically apply.
The Principal bears more cost risk, and the administrative requirements on both parties are substantially higher than under a lump sum.
Guaranteed Maximum Price
A hybrid of cost reimbursable and lump sum. The Contractor is paid for actual costs up to an agreed maximum, with savings below the maximum shared under the agreed gain-share mechanism. Costs above the maximum are absorbed by the Contractor.
Progress claims require open book cost tracking plus ongoing monitoring of cumulative expenditure against the cap.
Alliance and Target Cost
Used on complex or high-risk projects where the parties share risk and reward. Payment is typically on a cost reimbursable basis to an agreed target cost, with pain-share and gain-share provisions applying above and below that target.
The monthly claim must demonstrate that costs incurred are properly within scope under the agreed cost plan.
Payment Mechanisms
Alongside the pricing model, construction contracts include specific payment mechanisms to deal with types of work or cost that cannot be cleanly priced under the main model. These sit within or alongside the pricing model rather than replacing it.
- Provisional sums: An estimated allowance for a defined item that cannot be accurately priced at contract stage. The Contractor is paid the actual cost incurred, adjusted from the provisional sum.
- Prime cost items: Similar to provisional sums but applied to materials or goods specified by type and not yet priced. The Contractor is paid the actual cost plus the agreed margin or handling fee.
- Dayworks: A payment mechanism used for work that cannot be measured or valued under the main pricing model, typically arising from a Principal's direction for work of an indeterminate nature. The Contractor records time, plant and materials on agreed sheets that the Superintendent or Principal's Representative signs off. Dayworks amounts are then claimed in the relevant monthly progress claim at agreed rates. Sheets not contemporaneously signed create disputes at assessment.
- Rise and fall provisions: Adjust the contract price by reference to movements in nominated input cost indices. Where a rise and fall clause applies, the adjusted amount forms part of each progress claim. Where no such clause applies, the Contractor carries the input cost risk.
- Milestone payments: Tie payment to the achievement of defined project stages rather than monthly assessment. Milestones defined by reference to the Superintendent's or Principal's satisfaction introduce significant subjectivity into when payment falls due.
The Superintendent and the Principal's Representative
Under AS4000 and AS4000:2025, after receiving the Contractor's progress claim, the Superintendent must issue a payment certificate within a specified period. The payment certificate sets out the amount certified as due, and the Principal must then pay within the period specified in the Contract Particulars.
The Superintendent holds a dual function: acting as the Principal's agent in administering the contract, and performing the independent certifier role. Under AS4000, the Superintendent is required to act honestly and reasonably when exercising that certifier function. The Principal's Representative is not necessarily the Superintendent, and on many projects contract administration is shared between the Superintendent and other Principal staff.
Where Principal staff who are not the Superintendent are directing how claims are assessed or imposing payment procedures that have no contractual basis, the Contractor is entitled to identify and push back on that interference. Instructions from other Principal personnel that purport to override the Superintendent's certification function are not contractually founded unless the contract expressly provides for them. Whether a Superintendent's progress certificate also constitutes a payment schedule for BIFA purposes was considered by the Queensland Court of Appeal in RHG Construction Fitout and Maintenance Pty Ltd v Kangaroo Point Developments MP Property Pty Ltd [2021] QCA 117. Sofronoff P held at [35] that for a certificate to operate as a payment schedule under BIFA it must state "the amount of the payment, if any, the respondent proposes to make." A certificate that records only an assessed value does not meet that standard.
Preconditions to Payment
Most standard form contracts impose preconditions that the Contractor must satisfy before a progress claim is valid and before the payment period starts running. Understanding those preconditions before the project starts matters because a failure to meet them can delay payment without giving rise to a dispute that can readily be resolved under BIFA.
Under the unamended AS4000:2025, the Contractor submits a progress claim to the Superintendent at the interval agreed in the Contract Particulars, accompanied by documentation sufficient to allow assessment. Under AS2124, still in active use on many projects, the Contractor submits on or before the progress claim date and the Superintendent must issue a payment certificate within the time specified in the Annexure. Under NEC4, the Project Manager assesses payment at each assessment date and the Contractor is not required to submit a claim, though in practice Contractors submit applications for payment to support the assessment.
Common preconditions added through Special Conditions include requirements to provide a statutory declaration of compliance before each payment is released, requirements to provide a cost report or programme update before the claim is assessed, requirements to obtain Principal approval of variations before they can be included in a progress claim, and requirements tied to preceding milestone completion. Where those preconditions are contractual, failing to meet them may delay payment. Where they have no contractual basis, they may constitute the kind of administrative obstruction described in the experience section below.
Claiming Additional Amounts Throughout the Project
Your entitlement under a construction contract is not frozen at the original contract price. Throughout a project, a range of events and circumstances can give rise to additional payment claims, and identifying those entitlements as they arise is as important as managing the monthly claim cycle.
- Variations: Where the Principal instructs a change to scope, timing or method, or where work is carried out outside the agreed scope and qualifies as a variation under the contract.
- Extension of time and delay costs: Where a delay event that is the Principal's risk causes delay to the Works, giving rise to time relief and, depending on the contract, a money claim for prolongation costs.
- Latent conditions: Site conditions that differ materially from those a competent contractor would have anticipated at tender, entitling the Contractor to time and cost under AS4000 and AS4000:2025 provided notice is given promptly after discovery.
- Rise and fall adjustments: On contracts with a price adjustment mechanism, where input cost indices have moved, the adjustment is claimable in the monthly progress claim.
- Provisional sum adjustments: Where the actual cost of a provisional sum item differs from the contract allowance.
- Acceleration costs: Where the Contractor has been directed to accelerate, or has accelerated in response to circumstances that constitute a constructive direction, and has incurred additional costs as a result.
- Disruption costs: Where the Contractor's planned method has been disrupted by Principal-risk events, causing additional costs even where the overall project duration has not extended.
- Suspension costs: Where the Contractor is directed to suspend work, or is entitled to suspend work under BIFA following non-payment, and incurs costs as a consequence.
- Release of retention and performance security: Falling due at contractual trigger points, and must be formally claimed if the Principal does not release it once the trigger has been met.
- Statutory change costs: Where changes in legislation during the project affect the Contractor's cost of performance and the contract allocates that risk to the Principal.
One of the patterns I see regularly is a contract clause that, read in isolation, appears to set a reasonable payment period. The clause states that the payment period runs from the date on which the Principal receives a valid payment claim.
What then happens in practice is that the Principal's Representative contacts the Contractor after the claim is submitted and says the organisation cannot process payment against a payment claim, and that it needs a tax invoice instead. The Contractor is then told it cannot submit the tax invoice until the work has been formally "Accepted" by the Principal's Representative.
The Contractor reads the contract. There is no right for the Principal to formally Accept that category of work. Acceptance is not a mechanism that exists anywhere in the contract in relation to that work. The Principal's Representative has introduced an administrative requirement with no contractual foundation, and the practical effect is that the payment period never begins until the Principal decides it should begin.
When the Contractor raises this, the response is that cooperation and flexibility are important to the ongoing relationship, and that pressing the point will reflect poorly. From my observation, contractors wait three to four months beyond their contractual payment date on completed work because of that pressure. The lesson is to read the payment trigger carefully before the project starts, identify precisely what event starts the payment clock, and check whether the contract gives the Principal or its Representative any right to delay or condition that trigger. If it does not, the Contractor has a payment dispute, and is entitled to treat it as one.
How Payment Works Under BIFA
For Contractors Who Endorse, or Who Must Endorse
In jurisdictions where all payment claims are required to be endorsed under the relevant Security of Payment Act, and for contractors who choose to endorse in other jurisdictions, the following applies once the claim has been served.
Reference Dates
In Queensland, the right to serve a payment claim arises on a reference date. If the contract specifies reference dates, those govern. If the contract is silent, the default under BIFA is the last business day of each month in which construction work was first carried out, and the last day of each subsequent month. Reference dates currently apply in Queensland, South Australia, Tasmania and the Northern Territory. New South Wales and Western Australia (under the 2021 Act) do not use them. Victoria removed reference dates from April 2026 and the ACT removed them from March 2024. Serving a payment claim in Queensland before the relevant reference date is an error that can invalidate the BIFA claim.
Validity Requirements
A valid BIFA payment claim must identify the construction work or related goods and services, state the amount claimed, and include the endorsement wording referencing BIFA. The identification of the work does not need to meet a court pleadings standard, but must be sufficient for the respondent to understand what is being claimed from the contract and the surrounding circumstances. In Queensland, Contractors on non-residential projects must include a supporting statement with every BIFA payment claim, declaring whether all subcontractors and suppliers have been paid and, if not, identifying which have not been paid in full and the reasons.
Payment Timeframes in Queensland
The payment due date is the date stated in the contract. If the contract is silent, the statutory default under BIFA is 10 business days after the payment claim is given to the respondent. For work constituting "building work" under the Queensland Building and Construction Commission Act 1991 (Qld), BIFA caps the maximum payment period a contract can impose.
| Payment Relationship (Queensland) | Maximum Period (Building Work) | Statutory Default if Exceeded |
|---|---|---|
| Principal to Contractor | 15 business days from payment claim | 10 business days |
| Contractor to Subcontractor | 25 business days from payment claim | 10 business days |
| Other construction work (non-building) | As per contract | 10 business days if contract silent |
Payment Timeframes in Other Jurisdictions
Maximum payment timeframes differ across Australian states and territories. The table below sets out the current position. All figures are in business days from service of the payment claim unless noted.
| Jurisdiction | Principal to Contractor | Contractor to Subcontractor | Payment Schedule Response |
|---|---|---|---|
| Queensland | 15 BD (building work); 10 BD default | 25 BD (building work); 10 BD default | Earlier of contract period or 15 BD |
| New South Wales | 15 BD | 20 BD | 10 BD |
| Victoria | 20 BD (from April 2026 reforms) | 20 BD | 10 BD |
| Western Australia | 20 BD | 25 BD | 15 BD |
| South Australia | 15 BD | 15 BD | 15 BD |
| Tasmania | 10 BD (or as per contract) | 10 BD (or as per contract) | 10 BD (residential: 20 BD) |
| ACT | 10 BD | 10 BD | 10 BD |
| Northern Territory | As per contract or reasonable period | As per contract or reasonable period | No statutory payment schedule requirement under NT model |
BD = Business Days. These figures are a guide only. The legislation in each jurisdiction should be confirmed for any specific project, as the position in several states has been amended recently.
Payment Schedules
Under the contract, most standard forms require the Superintendent or Principal's Representative to issue a response to a payment claim within a specified period, whether as a payment certificate under AS4000 or a notice of dissatisfaction under other forms. Under BIFA, the respondent must either pay the full claimed amount by the due date or serve a payment schedule within the earlier of the period specified in the contract or 15 business days after receiving the payment claim.
A payment schedule under BIFA must state the amount the respondent proposes to pay and, for any amount withheld, the reasons for withholding it. In Queensland, courts will not infer reasons from ancillary documentation, per the principle confirmed in Minimax Fire Fighting Systems Pty Ltd v Bremore Engineering (WA) Pty Ltd [2007] QSC 333 and applied under BIFA. (Source: Holding Redlich, Security of Payment QLD.) The reasons must appear in the payment schedule document itself. A respondent who provides insufficient reasons is not permitted to raise additional reasons in a subsequent adjudication under the Security of Payment Act.
Standard and Complex Claims
BIFA distinguishes between standard payment claims (under $750,000 excluding GST) and complex payment claims ($750,000 or more). That distinction does not affect the content or validity requirements of the payment claim. It affects the adjudication timeframes if the claim is disputed under the Security of Payment Act.
Deciding Whether to Pursue Under BIFA
If the respondent pays the full scheduled amount by the due date, the matter is resolved regardless of which process was used. If the respondent disputes the claim in a payment schedule, or does not serve a payment schedule and does not pay the full amount, the contractor with a validly endorsed BIFA claim can apply for adjudication. Timing is critical. The window for making an adjudication application is 30 business days after receiving the payment schedule, or after the due date if no payment schedule was served. Missing that window closes the BIFA adjudication option for that claim.
For Contractors Who Do Not Endorse, or Who Choose Not to Pursue Under BIFA
A contractor who does not endorse a payment claim under BIFA, or who endorses but decides not to use the Security of Payment Act, proceeds under the contract only. Payment is due on the date the contract specifies. If the respondent does not pay by that date, the Contractor can pursue payment through the contractual dispute resolution process.
Most standard form contracts require the parties to attempt direct negotiation before escalating. Time limits apply to each step, and failing to follow the contractual process properly can prejudice the Contractor's position in subsequent proceedings. Where the contractual process is exhausted without resolution, the Contractor's options include arbitration (where the contract provides for it), litigation, or, for a subcontractor, subcontractors' charges under the Subcontractors' Charges Act 1974 (Qld). None of those options is as fast or as cost-effective as BIFA adjudication, and the Contractor cannot, at that later stage, convert an unendorsed contractual claim into a BIFA payment claim for the same payment period.
The Commercial Reality
Invoking the BIFA adjudication process is a step many Tier 2 and Tier 3 contractors approach with real caution. Going under the Security of Payment Act, and particularly escalating to adjudication, is widely read in the industry as a signal that the commercial relationship has broken down. For contractors who depend on repeat work from the same Principals or head contractors, that perception can be enough to close the door on future projects.
From my observation, working inside Tier 1 contractors and advising businesses across the contracting chain, the Security of Payment legislation is significantly underutilised at the lower levels of the chain. The right to prompt payment exists. Whether a contractor exercises it is a different question.
Ways the Principal May Reduce Your Payment Claim
The contract and how it is administered can both reduce what you actually receive against a progress claim. Some reductions are contractual and properly applied. Others are imposed without a proper basis, and understanding the difference matters when you are deciding whether to accept a payment schedule or push back.
Set-Off
Contractual set-off allows the Principal to reduce the amount it pays by reference to a separate amount it claims the Contractor owes under the same contract. Set-off clauses can be drafted broadly. The versions to pay close attention to are those that allow set-off of unliquidated amounts, meaning amounts not yet formally quantified or determined. Two phrasings used in Special Conditions to achieve that result are:
"The Principal may deduct from any amount otherwise payable to the Contractor any amount to which the Principal is or may become entitled under or in connection with this Contract, or otherwise."
"Any payment otherwise due to the Contractor may be reduced by any amount the Principal determines is owed to it by the Contractor."
Both formulations give the respondent broad discretion to reduce a progress claim on the basis of an amount that has not been established or agreed. Under the contract, the right to set-off must still be exercised in accordance with the contractual procedure. Under BIFA, a set-off used to reduce the scheduled amount must be identified in the payment schedule with sufficient reasons stated. A set-off raised for the first time in BIFA adjudication, without having been identified in the payment schedule, is generally not available to the respondent.
A related problem is where a Principal reduces a payment without a clear contractual right, providing inadequate reasons in the payment schedule. If the payment schedule fails to identify the contractual basis and the amount of the set-off with sufficient clarity, it may be deficient under BIFA.
Backcharges
A backcharge arises where the Principal incurs costs because the Contractor has not performed a contractual obligation, and seeks to recover those costs by deducting them from a progress payment. Common examples include the cost of cleaning or making safe work the Contractor was required to maintain, charges for shared site services where usage exceeded the allocated amount, and the cost of providing services the Contractor was obliged to supply but did not.
Under the contract, most standard forms give the Principal the right to impose a backcharge provided it has given the Contractor a written notice of the failure, allowed the specified time to remedy, and then incurred the cost of having the work done by others. A payment schedule that states "amount withheld pending resolution of costs associated with Contractor's failure to maintain site cleanliness" without identifying the notice given, the work done by others, and the cost incurred, does not provide the sufficient reason BIFA requires. Backcharges applied without any contractual basis at all may not be supportable in adjudication under the Security of Payment Act, and the payment schedule may be deficient as a result.
Abatement
Abatement is a common law right to reduce payment to reflect the diminished value of work delivered defectively or incompletely. Unlike set-off, abatement does not require a separate counterclaim. It goes to the value of what has actually been provided. Some contracts include provisions that operate similarly to abatement, allowing the Principal or Superintendent to reduce the certified value of work where it does not conform with the contract requirements, without characterising the reduction as a set-off or a separate claim. A respondent who raises abatement, or a contractual value reduction of that kind, in a payment schedule must state that it is doing so with sufficient particularity for the Contractor to understand the basis for the reduction.
Retention
Retention is the percentage of each progress payment withheld as security for the Contractor's performance. Standard form contracts including AS4000 typically set retention at 5% of each certified amount during construction, reducing to 2.5% after practical completion until the end of the Defects Liability Period, up to a cap. Special Conditions sometimes increase those percentages, extend the Defects Liability Period, or impose additional conditions for releasing the second tranche beyond what the standard form requires.
Retention is released in two stages: the first half on practical completion, and the balance at the end of the Defects Liability Period once the Contractor has rectified defects notified during that period. The second tranche is the one most commonly delayed without proper justification. Under BIFA's trust account framework, money held as retention on eligible contracts must be held in a retention trust account, not in the head contractor's general operating funds.
Liquidated Damages
Where the Contractor has not achieved practical completion by the Date for Practical Completion and an extension of time has not been granted covering that period, the Principal may levy liquidated damages at the rate specified in the Contract Particulars. Liquidated damages are most commonly applied as deductions from progress payments and can substantially reduce or eliminate a payment.
The entitlement to levy LDs is not automatic. It depends on whether the Date for Practical Completion was correctly set, whether any act of prevention by the Principal has extended time without a corresponding adjustment to that date, and whether outstanding extension of time claims would, if processed, cover the period in dispute. For detailed advice on liquidated damages and extension of time claims, see our Construction Disputes page.
Pay When Paid and Pay If Paid
BIFA expressly voids any provision of a construction contract that makes a party's liability to pay a progress payment conditional on that party having received payment from someone higher in the contractual chain. A subcontractor's or supplier's entitlement to a progress payment under the Security of Payment Act exists regardless of whether the Contractor has been paid by the Principal. Pay when paid provisions do not always use those words. Extended payment periods structured to track the head contract payment cycle, approval requirements tied to upstream certification events, and clauses that condition payment on the Principal having issued a payment certificate for the corresponding head contract claim can all have the same practical effect.
Pay if paid clauses go further, purporting to make the obligation to pay conditional not just on timing but on whether the head contractor is paid at all. Both types are void under BIFA and equivalent security of payment legislation in other Australian jurisdictions.
Pay When Paid and Pay If Paid Across Australia
All Australian jurisdictions prohibit pay when paid and pay if paid provisions under their security of payment legislation, though the specific statutory provision and its scope varies.
| Jurisdiction | Pay When Paid Prohibited | Statutory Provision |
|---|---|---|
| Queensland | Yes, under BIFA | s 99 Building Industry Fairness (Security of Payment) Act 2017 (Qld) |
| New South Wales | Yes | s 34 Building and Construction Industry Security of Payment Act 1999 (NSW) |
| Victoria | Yes | s 48 Building and Construction Industry Security of Payment Act 2002 (Vic) |
| Western Australia | Yes | s 53 Building and Construction Industry (Security of Payment) Act 2021 (WA) |
| South Australia | Yes | s 33 Building and Construction Industry Security of Payment Act 2009 (SA) |
| Tasmania | Yes | s 11 Building and Construction Industry Security of Payment Act 2009 (Tas) |
| ACT | Yes | s 42 Building and Construction Industry (Security of Payment) Act 2009 (ACT) |
| Northern Territory | Yes | s 10 Construction Contracts (Security of Payments) Act 2004 (NT) |
How to Get Paid When Payment Is Withheld
Where a payment claim is disputed or payment is withheld without a valid payment schedule, the Contractor, Subcontractor, Supplier or Trade Contractor has a range of options. The right option depends on the contract, the amount in dispute, the relationship between the parties, and the time limits that apply under BIFA and the contract.
Before escalating to formal proceedings, most standard form contracts require the parties to attempt direct negotiation or refer the matter to a senior representative for resolution. Under AS4000, that process is triggered by a notice of dispute. Under AS2124 it is a notice of claim. Under NEC4 it is an early warning or a notification to the Project Manager. These contractual processes run alongside, not instead of, BIFA. The statutory adjudication window under the Security of Payment Act continues to run while contractual negotiations are under way, and missing the statutory deadline is not excused by an ongoing negotiation.
Where a payment schedule reduces the claimed amount and the Contractor disagrees, the Contractor can proceed to adjudication under BIFA within 30 business days of receiving the payment schedule. Where no payment schedule is served and the full claimed amount is not paid by the due date, the Contractor can apply for adjudication or seek to recover the amount as a judgment debt, with the respondent's ability to defend the claim significantly restricted. Once an adjudicator issues a determination requiring payment, the respondent must pay the adjudicated amount within five business days. Where they do not, the Contractor can register the adjudicated amount as a judgment debt, give a payment withholding request to the party higher in the contractual chain, or give written notice of intention to suspend work.
Subcontractors also have access to subcontractors' charges under the Subcontractors' Charges Act 1974 (Qld) as a separate statutory mechanism. A subcontractors' charge is lodged over money payable in the chain above the head contractor, requiring amounts otherwise payable to the head contractor to be withheld pending resolution of the subcontractor's claim. Subcontractors' charges and BIFA adjudication are alternative remedies for the same claim and cannot be used in combination for the same amount.
| Mechanism | Who Can Use It | When Available | Can Run Alongside |
|---|---|---|---|
| Adjudication (BIFA Security of Payment Act) | Contractors, Subcontractors, Suppliers and Trade Contractors | After endorsed payment claim is disputed or unanswered | Suspension of work |
| Payment withholding request | Contractors, Subcontractors, Suppliers and Trade Contractors | After favourable adjudication determination unpaid within 5 business days | Court enforcement |
| Subcontractors' charges (Subcontractors' Charges Act 1974 (Qld)) | Subcontractors only | When amounts are owed under a subcontract | Suspension, but not adjudication for the same claim |
| Suspension of work | Contractors, Subcontractors, Suppliers and Trade Contractors | After non-payment following valid endorsed payment claim | Most other mechanisms |
| Court proceedings | All parties | Any payment dispute | Where not in conflict with another concurrent process |
Payment disputes under BIFA have strict time limits. The window for adjudication under the Security of Payment Act can close in 30 business days from the date of the payment schedule. If that window is missed, the statutory option for that claim is lost and the Contractor's remaining options are under the contract only.
If You Are Claiming Under the Security of Payment Act, or Have Received a Document from the Principal
BIFA and the Security of Payment Act impose strict time limits at every stage. If you have served a payment claim under BIFA and not received a payment schedule, or have received a payment schedule you disagree with, or have received a BIFA payment claim and are unsure how to respond, call Rachelle urgently. Missing a deadline can cost you the right to adjudicate a valid claim.
How Blaze Business & Legal Can Help
Blaze Business & Legal advises Contractors, Subcontractors, Suppliers and Trade Contractors on the full scope of payment issues under Queensland construction contracts, from payment provisions at contract execution stage through to disputed payment claims, adjudication strategy and enforcement under BIFA and the Security of Payment Act.
If your contract has not yet been signed, the right time to consider the payment provisions is before you are bound by them. A Construction Contract Review covers the payment clause, Special Conditions and Annexures together, so that you understand what the payment mechanics mean in practice across the project, and can negotiate changes before signing.
Where a payment claim has already been disputed, or adjudication under the Security of Payment Act is being considered, the advice is specific to the facts: which options are available, what the procedural steps are and in what sequence, and what the time limits are for each. Rachelle can work with you on both the legal strategy and the commercial position, maintaining the front-end legal and commercial oversight across the matter.
For businesses dealing with payment issues across multiple projects, or that want standing legal support without the cost of in-house counsel, Rachelle's External General Counsel retainer provides ongoing coverage. Where matters escalate to formal dispute proceedings, Rachelle works alongside litigation specialists while maintaining the front-end legal and commercial strategy.
FAQs About Construction Contract Payment in Queensland
In Queensland and all jurisdictions except the Northern Territory, a payment claim must carry the statutory endorsement under the relevant Security of Payment Act to trigger the adjudication process. Without the endorsement, the claim is a contractual claim only, and adjudication under BIFA is not available for that particular claim.
Many contractors include the statutory endorsement on all invoices as standard practice. That does not commit them to pursuing the matter under BIFA if a dispute arises. The decision to invoke adjudication is a separate one, made when the dispute arises.
A reference date is the date on or after which a payment claim can be served under BIFA and equivalent security of payment legislation. In Queensland, if the contract specifies reference dates, those govern. If the contract is silent, the default under BIFA is the last business day of each month in which construction work was first carried out, and the last day of each subsequent month.
Reference dates currently apply in Queensland, South Australia, Tasmania and the Northern Territory. New South Wales and Western Australia (under the 2021 Act) do not use them. Victoria removed reference dates from April 2026 and the ACT removed them from March 2024. Serving a payment claim in Queensland before the relevant reference date is an error that can invalidate the claim under BIFA.
A valid payment claim under BIFA must identify the construction work or related goods and services, state the amount claimed, and include the endorsement referencing the Building Industry Fairness (Security of Payment) Act 2017 (Qld). All three requirements must be met.
The identification of the work does not require court pleadings precision, but must be sufficient for the respondent to understand what is being claimed from the contract and the surrounding circumstances. Contractors on non-residential projects must also include a supporting statement with every payment claim, declaring whether all subcontractors and suppliers have been paid and, if not, identifying which have not been paid in full and the reasons.
A payment schedule is the respondent's written response to a BIFA payment claim under the Security of Payment Act. It must state the amount the respondent proposes to pay and, for any amount withheld, the reasons for withholding it. Those reasons must appear in the payment schedule document itself. In Queensland, courts will not infer reasons from ancillary documentation.
A respondent who fails to serve a valid payment schedule within the required time and who does not pay the full claimed amount by the due date becomes liable for the full claimed amount, with very limited ability to contest that liability in subsequent proceedings under BIFA.
The Principal can state a set-off, backcharge or liquidated damages deduction as a reason for withholding part of the claimed amount, provided those reasons are set out in sufficient detail in the payment schedule itself. Under the contract, the Principal must also exercise any set-off or backcharge right in accordance with the contractual procedure before deducting it from a progress payment.
A set-off or backcharge raised for the first time in BIFA adjudication, without having been identified in the payment schedule, is generally not available to the respondent. Backcharges that have not been properly notified and substantiated, and set-off amounts not quantified or identified by reference to a specific contractual entitlement, may not constitute sufficient reasons for the purposes of a valid payment schedule under the Security of Payment Act.
Payment is due on the date stated in the contract. If the contract is silent, the statutory default under BIFA is 10 business days after the payment claim is given to the respondent. For construction work constituting "building work" under the Queensland Building and Construction Commission Act 1991 (Qld), any contractual payment period exceeding 15 business days from a Principal to a Contractor, or exceeding 25 business days from a Contractor to a Subcontractor, is void for building work and the 10 business day default applies instead.
Retention is a percentage of each progress payment withheld as security for the Contractor's performance, typically 5% during construction reducing to 2.5% after practical completion. It is released in two stages: the first half on practical completion, and the balance at the end of the Defects Liability Period once notified defects have been rectified.
On eligible contracts under BIFA's trust account regime, retention must be held in a retention trust account rather than in the head contractor's general operating funds. Where retention is not released after the contractual trigger has been met, the failure to release can be the subject of a BIFA payment claim and adjudication under the Security of Payment Act.
Adjudication under BIFA and the Security of Payment Act is a fast-track statutory process resulting in an interim binding determination enforceable as a judgment debt, available to Contractors, Subcontractors, Suppliers and Trade Contractors. Subcontractors' charges under the Subcontractors' Charges Act 1974 (Qld) are a separate mechanism available only to subcontractors, allowing a charge to be lodged over money payable in the chain above the head contractor.
The two remedies are alternatives for the same claim and cannot be used in combination. Adjudication is generally faster and more commonly used for disputed payment claims. Subcontractors' charges may be more useful where the BIFA adjudication pathway is not available, for example where the contract has been terminated.
No. BIFA voids any provision that makes a party's obligation to pay a progress payment conditional on receiving payment from above. A subcontractor's or supplier's entitlement to a progress payment under the Security of Payment Act exists regardless of whether the Contractor has been paid. Pay if paid clauses, which purport to make the obligation to pay conditional on the head contractor being paid at all, are similarly void under BIFA.
The respondent must pay the adjudicated amount within five business days of receiving the adjudicator's decision. If they do not, the Contractor can register the adjudicated amount as a judgment debt in the relevant Queensland court, give a payment withholding request to the party higher in the contractual chain (requiring that party to withhold amounts otherwise payable to the respondent up to the adjudicated amount), or give written notice of intention to suspend work.
The BIFA adjudication determination is enforceable but does not enforce itself. Each of those steps has its own procedural requirements, and timing matters at each stage.
Request a Fixed-Price Quote
Payment claims, payment schedule responses and adjudication applications under BIFA all operate under strict time limits. The right time to seek advice is before the next deadline in the process, not after it has passed.
Rachelle provides fixed-price advice on payment claim issues, BIFA compliance, payment clause review and adjudication strategy for Queensland Contractors, Subcontractors, Suppliers and Trade Contractors. If your contract has not yet been signed, a Construction Contract Review is the most cost-effective way to understand your payment position before you are bound by it.
Rachelle Hare
Construction Lawyer, Business Adviser and Commercial Manager|Blaze Business & Legal
Rachelle has more than 25 years of experience in construction law, business advisory, commercial management, contract administration and construction business structuring. Her career includes senior in-house legal roles at Tier 1 and Tier 2 construction companies including Thiess, Laing O’Rourke and Acciona, and private practice experience at top-tier law firms Corrs Chambers Westgarth and McCullough Robertson. She also spent over six years as a senior commercial manager on Defence and Tier 2 Construction and Technology Projects, including 8 months as Deputy Program Manager on a construction and technology program of National significance. At Blaze Business & Legal, Rachelle works alongside Shannon Drew to provide integrated construction law, financial management, commercial and business advisory services to construction businesses across Australia.
Structure. Strategy. Systems. Success.
Let’s Chat About How We Can Help You
- Contact us to discuss how we can help you and your construction business
- No-obligation quote
- We work to your budget and timeframes
Call Us
Email Us
Send Us a Message