Building and Construction Law Terms Australia - Glossary
1. Acceleration
Short Meaning: Measures taken to speed up construction progress without altering the contract completion date.
Longer Explanation: Acceleration occurs when a contractor is required to hasten the construction work to meet the agreed project timeline. This can involve increasing manpower, working overtime, or using additional resources to expedite the work. Acceleration can be directed by the client or can be voluntary if the contractor identifies potential delays and takes preemptive action. Costs associated with acceleration typically require approval and may be subject to claims for additional payment.
How this term is commonly used: โThe client requested acceleration of the project to ensure the building was completed before the holiday season.โ
2. Adjudication
Short Meaning: A quick dispute resolution process used in construction contracts, particularly under security of payment legislation.
Longer Explanation: Adjudication is a method of resolving disputes in the construction industry without resorting to lengthy and expensive litigation. It allows parties to obtain a binding decision from an adjudicator, usually within a short timeframe, which can be enforced until the dispute is finally resolved through arbitration or court proceedings. In Australia, adjudication is commonly used under security of payment laws to ensure contractors and subcontractors are paid for their work.
How this term is commonly used: โThe contractor referred the payment dispute to adjudication under the Security of Payment Act.โ
3. Adverse Possession
Short Meaning: A legal principle allowing someone to claim ownership of land after continuous and open possession for a certain period without the legal owner's consent.
Longer Explanation: Adverse Possession is a doctrine in Australian property law that allows a person to claim ownership of land if they have occupied it openly and continuously for a period, typically 12 years, without the owner's permission. This principle can apply to construction projects, particularly in disputes over boundaries or encroachments. The claimant must prove uninterrupted possession, use, and control of the land in question.
How this term is commonly used: โThe developer claimed adverse possession over a strip of land that had been used as part of the project for over 15 years.โ
4. Amendment
Short Meaning: A formal alteration to the terms of a contract.
Longer Explanation: An amendment is a change or addition made to a contract after it has been signed. This can include changes to the scope of work, timelines, payment terms, or other critical elements of the contract. Amendments must be agreed upon by all parties involved and are usually documented in writing to ensure clarity and enforceability. Without a formal amendment, any changes made to the original contract may not be legally binding.
How this term is commonly used: โThe parties signed an amendment to extend the project completion date by two months.โ
5. Anticipatory Breach
Short Meaning: When one party indicates they will not fulfil their contractual obligations before they are due.
Longer Explanation: An anticipatory breach occurs when one party to a contract communicates, either through words or actions, that they will not be able to meet their contractual obligations. This breach allows the non-breaching party to take legal action or terminate the contract before the breach actually occurs. It provides a remedy for the non-breaching party, allowing them to mitigate potential losses.
How this term is commonly used: โThe builderโs statement that they would not be able to complete the project on time constituted an anticipatory breach.โ
6. Arbitration
Short Meaning: A private dispute resolution process where an arbitrator makes a binding decision.
Longer Explanation: Arbitration is a form of alternative dispute resolution where a neutral third party, known as an arbitrator, hears the evidence and arguments from the parties involved in a dispute and then makes a decision. This decision is usually binding and enforceable, much like a court judgment. Arbitration is often preferred in construction contracts for its confidentiality, speed, and the ability to choose an arbitrator with specific expertise in construction law.
How this term is commonly used: โThe construction contract included an arbitration clause, requiring any disputes to be resolved through arbitration rather than court litigation.โ
7. As-Built Drawings
Short Meaning: Final drawings submitted by the contractor upon completion, showing the construction as it was actually built.
Longer Explanation: As-built drawings are an essential part of the construction documentation process in Australia. They reflect any changes or modifications made during construction, providing an accurate record of the completed project. These drawings are crucial for future maintenance, renovations, or legal disputes, as they detail the actual specifications, dimensions, and materials used in the project. They differ from the original design drawings, which may not account for on-site adjustments.
How this term is commonly used: โThe council required submission of the as-built drawings before issuing the final occupancy certificate.โ
8. Asbestos Register
Short Meaning: A record of the location and condition of asbestos-containing materials in a building.
Longer Explanation: An asbestos register is a mandatory document for buildings constructed before the year 2004 in Australia, detailing the location, condition, and management plan for asbestos-containing materials. The register is essential for ensuring that asbestos is safely managed and that risks to health are minimised during construction, renovation, or demolition. Compliance with asbestos regulations is crucial to protect workers and occupants from exposure to hazardous asbestos fibres.
How this term is commonly used: โThe buildingโs asbestos register was reviewed before renovation work commenced to ensure all asbestos-containing materials were handled safely.โ
9. Assignment
Short Meaning: The transfer of contractual rights or obligations to another party.
Longer Explanation: In Australian construction contracts, assignment refers to the process where one party transfers its rights or obligations under the contract to a third party. This is commonly seen when a contractor assigns its rights to receive payment to a financial institution as security for a loan. Assignments usually require the consent of the other party in the contract and must be documented to be enforceable. It is important to note that while rights can be assigned, obligations generally cannot be assigned without agreement.
How this term is commonly used: โThe developer assigned the payment rights under the contract to their financier.โ
10. Backcharge
Short Meaning: A charge levied by the client against the contractor for defective work or for failure to meet contractual obligations.
Longer Explanation: A backcharge occurs when a client deducts costs from payments due to the contractor as a result of the contractorโs failure to perform or meet the standards outlined in the contract. This could include costs for rectifying defective work, delays, or additional expenses incurred by the client due to the contractorโs actions. In Australia, backcharges must be justified and documented, as they can lead to disputes if not handled transparently.
How this term is commonly used: โThe contractor received a backcharge for failing to meet the specified quality standards in the flooring installation.โ
11. Back-to-Back Contract
Short Meaning: A contract that mirrors the terms of the main contract between a contractor and a client, typically used with subcontractors.
Longer Explanation: A Back-to-Back Contract is a contract between a main contractor and a subcontractor that replicates the terms and conditions of the main contract between the contractor and the client. In Australia, this approach ensures consistency across all contractual agreements, reducing the risk of disputes and ensuring that subcontractors are bound by the same obligations as the main contractor. This method is particularly useful for managing complex projects with multiple subcontractors.
How this term is commonly used: โThe main contractor signed a back-to-back contract with the roofing subcontractor, ensuring that all contractual obligations flowed down from the client.โ
These additional terms complete the glossary, making it more comprehensive and covering a broader range of construction law concepts relevant to the Australian construction industry.
12. Bank Guarantee
Short Meaning: A financial security provided by a bank on behalf of the contractor to guarantee performance or payment.
Longer Explanation: A bank guarantee is commonly used in Australian construction contracts as a form of security to protect the client in case the contractor fails to fulfil their contractual obligations. The bank provides a guarantee to the client that they will receive payment up to a certain amount if the contractor defaults. This provides the client with financial protection while also allowing the contractor to demonstrate their reliability and financial stability.
How this term is commonly used: โThe bank guarantee was provided to the client as security for the contractorโs performance on the high-rise development.โ
13. Best Endeavours
Short Meaning: An obligation to take all reasonable steps to fulfil a contractual duty, but without guaranteeing the outcome.
Longer Explanation: In construction contracts, a โbest endeavoursโ clause requires a party to take all reasonable steps to achieve a specific objective. In Australia, this obligation is less strict than an absolute requirement but still demands significant effort. The party is not required to sacrifice their own interests but must act diligently and in good faith to meet the contractual obligations.
How this term is commonly used: โThe contractor was required to use best endeavours to complete the project ahead of schedule.โ
14. Bill of Quantities (BOQ)
Short Meaning: A detailed list of materials, parts, and labour required for a construction project, with estimated costs.
Longer Explanation: A Bill of Quantities (BOQ) is a comprehensive document used in construction projects to itemise all the materials, parts, and labour required to complete the project. In Australia, the BOQ is typically prepared by a quantity surveyor and serves as the basis for tendering and cost control. It breaks down the project into measurable components, allowing for more accurate cost estimation and budget management. The BOQ helps ensure that all aspects of the project are accounted for and provides a common reference point for the client, contractor, and subcontractors.
How this term is commonly used: โThe quantity surveyor prepared the Bill of Quantities, which was used to compare bids from different contractors.โ
15. Bond
Short Meaning: A financial security provided by a contractor to guarantee performance, payment, or the fulfilment of other contractual obligations.
Longer Explanation: In the Australian construction industry, bonds are used as a form of security to ensure that contractors fulfil their contractual obligations. There are various types of bonds, including performance bonds, payment bonds, and bid bonds. Performance bonds guarantee that the contractor will complete the project as per the contract terms. Payment bonds ensure that subcontractors and suppliers are paid. Bonds protect the client from financial loss if the contractor fails to meet their obligations.
How this term is commonly used: โThe contractor provided a performance bond to ensure the project would be completed on time and to the required standards.โ
16. Breach of Contract
Short Meaning: The failure to fulfil the terms as agreed in a contract.
Longer Explanation: A breach of contract in the Australian construction industry occurs when one party does not meet their obligations as outlined in the contract. This can include failures to perform work, meet deadlines, or deliver materials as specified. Breaches can be minor (partial breach) or major (material breach) and can result in legal action, including claims for damages or contract termination. The type and consequences of a breach depend on the contract terms and the severity of the non-compliance.
How this term is commonly used: โThe contractor### 14. Breach of ContractShort Meaning: The failure to fulfil the terms as agreed in a contract.
Longer Explanation: A breach of contract in the Australian construction industry occurs when one party does not meet their obligations as outlined in the contract. This can include failures to perform work, meet deadlines, or deliver materials as specified. Breaches can be minor (partial breach) or major (material breach) and can result in legal action, including claims for damages or contract termination. The type and consequences of a breach depend on the contract terms and the severity of the non-compliance.
How this term is commonly used: โThe contractorโs failure to complete the work on time was considered a material breach of contract.โ
17. Brownfield Project
Short Meaning: Redevelopment or reuse of previously developed land, often complicated by environmental contamination.
Longer Explanation: A Brownfield project involves the redevelopment or reuse of land that has been previously developed, often in urban areas. In Australia, these projects are challenging due to potential contamination from previous industrial use, requiring environmental remediation before construction can proceed. Brownfield projects are important for revitalising urban areas, reducing urban sprawl, and making efficient use of existing infrastructure.
How this term is commonly used: โThe developer took on a Brownfield project to transform the old industrial site into a new residential community.โ
18. Builder's Licence
Short Meaning: A licence required by builders to undertake certain types of construction work, governed by state regulations.
Longer Explanation: In Australia, a builderโs licence is mandatory for anyone undertaking building work over a certain value, which varies by state. This licence ensures that the builder meets the necessary qualifications, experience, and knowledge to perform construction work safely and to the required standard. Each state and territory has its own licensing authority, and unlicensed work can result in significant fines and legal consequences.
How this term is commonly used: โThe builderโs licence must be renewed annually to ensure compliance with state regulations.โ
19. Building Contract
Short Meaning: The formal agreement between a client and contractor detailing the scope, terms, and conditions of a construction project.
Longer Explanation: A building contract in Australia outlines the rights, responsibilities, and obligations of both the client (often referred to as the principal) and the contractor. It typically includes details such as the scope of work, payment terms, deadlines, and dispute resolution mechanisms. This contract is legally binding and serves as the foundation for managing the construction project, ensuring that both parties understand their roles and the expectations for the work.
How this term is commonly used: โThe building contract was signed before the project commenced, outlining the payment schedule and completion dates.โ
20. Claim
Short Meaning: A demand for compensation or extension of time made by one party to another under a construction contract.
Longer Explanation: In the Australian construction industry, a claim is typically made by a contractor to the client for additional payment or time due to unforeseen circumstances or changes in the project scope. Claims can arise from delays, variations, or unexpected site conditions. Proper documentation and timely submission are crucial, as claims can lead to disputes if not managed correctly. The process for handling claims is usually detailed in the contract.
How this term is commonly used: โThe contractor submitted a claim for additional costs incurred due to unexpected ground conditions.โ
21. Completion Date
Short Meaning: The date by which the construction work must be finished, as stated in the contract.
Longer Explanation: The completion date is a critical element in Australian construction contracts, representing the deadline by which the contractor must complete the work. Failure to meet this date can result in penalties such as liquidated damages unless an extension of time is granted. The completion date is agreed upon at the contract's outset and can be affected by delays, variations, or other factors as outlined in the contract.
How this term is commonly used: โThe completion date was extended due to delays caused by adverse weather conditions.โ
22. Condition Precedent
Short Meaning: A condition that must be met before a contract is legally enforceable.
Longer Explanation: In construction contracts, a condition precedent refers to a specific requirement that must be satisfied before the contract or a particular obligation within the contract becomes effective. This could include obtaining planning approvals, securing financing, or completing preliminary works. In Australia, failing to meet a condition precedent means that the parties are not bound to proceed with the contract until the condition is fulfilled.
How this term is commonly used: โThe contract included a condition precedent requiring the approval of the development application before construction could commence.โ
23. Constructive Acceleration
Short Meaning: The act of speeding up work due to perceived delays, without formal instruction, often leading to a claim for additional costs.
Longer Explanation: Constructive acceleration occurs when a contractor speeds up work to avoid potential penalties due to delays, even though a formal extension of time has not been granted. In Australia, contractors may claim additional compensation for constructive acceleration if they can prove that they accelerated in response to delays for which they were not responsible. This concept is significant in projects with tight deadlines and complex scheduling.
How this term is commonly used: โThe contractor claimed additional costs for constructive acceleration after the client refused to grant an extension of time.โ
24. Construction Certificate (CC)
Short Meaning: A certificate issued by a local authority confirming that the construction plans comply with relevant building codes and regulations.
Longer Explanation: In Australia, a Construction Certificate (CC) is a crucial document that confirms that the construction plans for a project comply with the Building Code of Australia (BCA) and relevant local regulations. The CC must be obtained before construction can begin and is issued by a local council or a private certifier. This certificate ensures that the project meets all necessary safety, health, and structural requirements, and is a prerequisite for commencing building work legally.
How this term is commonly used: โThe builder received the Construction Certificate from the local council, allowing the project to move forward to the construction phase.โ
25. Construction Management
Short Meaning: A procurement method where the contractor manages the project on behalf of the client but does not carry out the physical work.
Longer Explanation: Construction management is a project delivery system commonly used in Australia, where the client engages a construction manager to oversee and coordinate the construction process. The construction manager acts as the clientโs agent, managing multiple trade contractors who perform the actual construction work. This method allows for greater flexibility and control over the project, as the client can directly engage specialists for different parts of the work.
How this term is commonly used: โThe client opted for construction management to maintain direct control over the selection of subcontractors.โ
26. Construction Management at Risk (CMAR)
Short Meaning: A method where the construction manager acts as a consultant during design and as the general contractor during construction.
Longer Explanation: Construction Management at Risk (CMAR) is a project delivery method where the construction manager is involved early in the design phase as a consultant and later takes on the role of the general contractor during construction. In Australia, CMAR is used for complex projects that benefit from the construction managerโs input on cost, schedule, and constructability during the design process. The construction manager assumes the risk of delivering the project within a guaranteed maximum price (GMP).
How this term is commonly used: โThe university used the CMAR approach for its new science building to ensure that the project stayed within budget and on schedule.โ
27. Cost Plus
Short Meaning: A method of payment based on the actual cost of labour, materials, and equipment used, plus a fee.
Longer Explanation: "Cost Plus" is a payment method used in construction where the contractor is reimbursed for the actual costs of labour, materials, and equipment, plus an agreed fee for overhead and profit. This method is typically used when the scope of work is not well-defined or when work needs to be completed quickly under urgent conditions. In Australia, Cost Plus is used in situations where it is impractical to establish a fixed price, providing flexibility for both the client and the contractor. This method of contracting is often combined with open book record-keeping, to allow the client to verify the contractor's costs incurred. While it offers transparency and flexibility, it requires close cost monitoring by the client to avoid excessive spending.
How this term is commonly used: โThe renovation was carried out under a Cost Plus Percentage Fee contract due to the uncertainty of the existing buildingโs condition.โ
28. Cultural Heritage Management Plan (CHMP)
Short Meaning: A plan required for projects that may impact Indigenous cultural heritage, ensuring compliance with relevant legislation.
Longer Explanation: In Australia, a Cultural Heritage Management Plan (CHMP) is a document required for projects that may affect areas of Indigenous cultural significance. The plan outlines how cultural heritage will be protected and managed throughout the construction process. It is a legal requirement under various state and territory laws and is developed in consultation with Indigenous communities to ensure their cultural sites are preserved.
How this term is commonly used: โThe development required a Cultural Heritage Management Plan to ensure compliance with the Aboriginal Heritage Act.โ
29. Damages
Short Meaning: Compensation awarded for loss or injury caused by a breach of contract.
Longer Explanation: Damages are a form of monetary compensation awarded to a party who has suffered a loss or injury due to another partyโs breach of contract. In Australian construction law, damages are intended to place the injured party in the position they would have been in if the contract had been performed as agreed. The amount and type of damages awarded depend on the nature of the breach and the losses incurred.
How this term is commonly used: โThe contractor was ordered to pay damages for failing to complete the project on time.โ
30. Defects Liability Period
Short Meaning: The period after practical completion during which the contractor must rectify any defects.
Longer Explanation: The defects liability period is a specified time following the practical completion of a construction project during which the contractor is responsible for rectifying any defects that arise. In Australia, this period typically lasts for 6 to 12 months, depending on the contract. The contractor is required to fix any issues identified during this period at no additional cost to the client, ensuring the quality and integrity of the construction work.
How this term is commonly used: โThe defects liability period allowed the client to identify and report any issues that needed to be fixed by the contractor.โ
31. Delay Costs
Short Meaning: Costs incurred due to delays in the construction process, which may be recoverable depending on the contract terms.
Longer Explanation: Delay costs refer to the financial losses or additional expenses incurred due to delays in the construction project. These can include increased labour costs, extended equipment hire, and penalties for late completion. In Australia, contractors may be entitled to recover delay costs if the delay is caused by factors beyond their control, such as adverse weather or changes to the project scope. The ability to claim these costs depends on the terms outlined in the contract.
How this term is commonly used: โThe contractor submitted a claim for delay costs after the project was delayed due to unforeseen site conditions.โ
32. Design and Construct (D&C)
Short Meaning: A type of contract where the contractor is responsible for both the design and construction of the project.
Longer Explanation: The Design and Construct (D&C) contract is a popular procurement method in Australia, where a single contractor is responsible for both the design and construction phases of a project. This type of contract provides a streamlined approach, reducing the clientโs risk by having one entity accountable for the entire project. D&C contracts can lead to cost savings and faster project delivery, as the contractor can optimise the design to suit their construction methods.
How this term is commonly used: โThe developer opted for a Design and Construct contract to ensure a faster project turnaround.โ
33. Design-Build (DB)
Short Meaning: A method where design and construction services are contracted by a single entity.
Longer Explanation: In the Design-Build (DB) method, the client contracts a single entity to provide both design and construction services. This approach is widely used in Australia for its efficiency and potential cost savings, as it allows for faster project delivery by overlapping the design and construction phases. The Design-Build contractor is responsible for all aspects of the project, from initial concept to completion, reducing the clientโs administrative burden and simplifying communication. This term is used interchangably with Design & Construct in Australia.
How this term is commonly used: โThe hospital project was delivered using the Design-Build method, which shortened the overall project timeline.โ
34. Design-Bid-Build (DBB)
Short Meaning: A traditional project delivery method where design and construction are separate contracts.
Longer Explanation: Design-Bid-Build (DBB) is a conventional project delivery method where the client first hires a designer (architect or engineer) to create the project design and then selects a contractor through a bidding process to execute the construction. In Australia, DBB is commonly used for projects where the design must be fully completed before construction begins. This method allows for competitive bidding but can lead to longer project timelines due to the sequential nature of the process.
How this term is commonly used: โThe council chose the Design-Bid-Build approach for the new library to ensure that the design was fully completed before selecting a contractor.โ
35. Development Application (DA)
Short Meaning: A formal request submitted to a local council seeking approval for a proposed### 28. Development Application (DA)Short Meaning: A formal request submitted to a local council seeking approval for a proposed development or construction project.
Longer Explanation: A Development Application (DA) is a detailed submission made to a local council in Australia, seeking approval to carry out a development project. The DA includes plans, drawings, and supporting documents that outline the scope, design, and impact of the proposed development. The approval process involves assessing the project against local planning regulations, community feedback, and environmental considerations. Approval of a DA is a critical step before obtaining a Construction Certificate and beginning work.
How this term is commonly used: โThe architect submitted the Development Application to the council for approval of the new residential development.โ
36. Dispute Resolution Board (DRB)
Short Meaning: A board appointed at the start of a project to help resolve disputes that arise during the project.
Longer Explanation: A Dispute Resolution Board (DRB) is an independent panel of experts appointed at the outset of a construction project to assist in resolving disputes as they arise. In Australia, DRBs are used in large or complex projects to avoid the cost and time delays associated with litigation or arbitration. The board typically meets regularly during the project to monitor progress and facilitate the resolution of any disputes before they escalate.
How this term is commonly used: โThe Dispute Resolution Board was instrumental in resolving the disagreement over contract variations.โ
37. Due Diligence
Short Meaning: The investigation and analysis of a project to assess risks before entering into a contract.
Longer Explanation: Due diligence is the process of thoroughly investigating and evaluating a construction project before entering into a contract or making an investment. In Australia, due diligence involves assessing various aspects of the project, including legal, financial, environmental, and technical factors. This process helps identify potential risks and ensures that all parties are fully informed before committing to the project.
How this term is commonly used: โThe developer conducted extensive due diligence before purchasing the land for the new development.โ
38. Easement
Short Meaning: A right granted to a third party to use part of the land for a specific purpose, such as access or utilities.
Longer Explanation: An easement is a legal right granted to a third party to use a portion of another party's land for a specific purpose, such as providing access or running utilities like water or electricity. In Australia, easements are commonly found in construction projects where services or access paths need to cross neighbouring properties. Easements are typically registered on the property title and remain in place even if the property changes ownership.
How this term is commonly used: โThe construction plans included an easement to allow for the installation of a sewer line across the neighbouring property.โ
39. Environmental Impact Assessment (EIA)
Short Meaning: A process of evaluating the potential environmental impacts of a proposed construction project.
Longer Explanation: An Environmental Impact Assessment (EIA) is a comprehensive evaluation process used to assess the potential environmental effects of a proposed construction project. In Australia, EIAs are required for projects that may have significant environmental impacts, such as large infrastructure developments or projects in sensitive areas. The EIA process includes public consultation, scientific studies, and the development of mitigation strategies to minimise negative environmental effects. The findings of the EIA are used to inform decision-making and ensure sustainable development.
How this term is commonly used: โThe Environmental Impact Assessment identified several potential impacts, leading to modifications in the project design to mitigate these effects.โ
40. Extensions of Time (EOT)
Short Meaning: A formal extension of the contract completion date, usually granted due to delays beyond the contractorโs control.
Longer Explanation: An Extension of Time (EOT) is a formal adjustment to the project completion date granted when delays occur that are beyond the contractor's control. In Australian Standard Contracts like AS 2124 and AS 4000, EOT provisions are critical for protecting contractors from liquidated damages due to delays. EOT claims must be substantiated with evidence and documentation, and are usually related to qualifying causes of delay. Properly managing EOTs is essential for maintaining project schedules and avoiding disputes.
How this term is commonly used: โThe contractor applied for an Extension of Time due to delays caused by unseasonable weather conditions.โ
41. Estoppel
Short Meaning: A legal principle preventing a party from arguing something contrary to what is implied by their previous actions or statements.
Longer Explanation: Estoppel is a legal doctrine that prevents a party from asserting a claim or fact that is contradictory to their previous actions or statements if it would be unfair to the other party who relied on those actions or statements. In Australian construction law, estoppel can arise when one party's conduct leads another party to believe in a certain set of facts, and they act upon that belief to their detriment.
How this term is commonly used: โThe developer was estopped from denying the contractorโs claim after previously approving the work.โ
42. Exclusion Clause
Short Meaning: A clause that limits or excludes liability for certain risks or damages under the contract.
Longer Explanation: An exclusion clause in a construction contract is a provision that seeks to limit or exclude the liability of one party for specific risks or damages. In Australia, these clauses must be clearly worded and brought to the attention of all parties at the time of contracting to be enforceable. Exclusion clauses are often used to manage risks related to delays, force majeure events, or defects in work.
How this term is commonly used: โThe contract included an exclusion clause that limited the contractorโs liability for delays caused by extreme weather.โ
43. FIDIC
Short Meaning: The International Federation of Consulting Engineers, which produces standard forms of contract used globally, including in Australia.
Longer Explanation: FIDIC (Fรฉdรฉration Internationale des Ingรฉnieurs-Conseils) is an international organisation that publishes standard forms of contract widely used in the construction industry, including in Australia. FIDIC contracts are commonly used for complex and international projects due to their well-established procedures and balance between parties' interests. These contracts are particularly useful in projects that involve multiple jurisdictions or international parties.
How this term is commonly used: โThe FIDIC contract was chosen for the international infrastructure project due to its robust dispute resolution mechanisms.โ
44. Final Account
Short Meaning: The final statement of the cost of the project, agreed upon by the client and contractor at the end of the project.
Longer Explanation: The final account is a comprehensive statement prepared at the end of a construction project that details the total cost of the work completed. In Australia, this document is essential for closing out the project, as it includes all variations, adjustments, and claims made during the course of the work. Both the client and contractor must agree on the final account before the final payment is made.
How this term is commonly used: โThe contractor and client reached an agreement on the final account, clearing the way for final payment.โ
45. Force Majeure
Short Meaning: Events outside the control of the parties, such as natural disasters, which can excuse contractual obligations.
Longer Explanation: Force majeure refers to extraordinary events or circumstances beyond the control of the contracting parties that prevent the fulfilment of contractual obligations. In Australian construction contracts, force majeure clauses typically cover events like natural disasters, wars, strikes, or pandemics. When a force majeure event occurs, the affected party may be excused from performing their contractual duties without penalty, depending on the specific terms of the contract.
How this term is commonly used: โThe project was delayed due to a force majeure event, and the contractor was granted an extension of time.โ
46. Front-End Engineering Design (FEED)
Short Meaning: The initial phase of project development, focusing on technical requirements and cost estimation.
Longer Explanation: Front-End Engineering Design (FEED) is a crucial stage in the project development process where the technical requirements, project scope, and cost estimates are defined. In Australia, FEED is typically conducted after the feasibility study, focusing on key design and engineering decisions that will influence the project's final outcome. FEED helps in minimising risks by ensuring that all technical and cost aspects are well understood before moving to the detailed design and construction phases.
How this term is commonly used: โThe FEED process was completed to ensure the project scope was clearly defined before moving to detailed design.โ
47. Gantt Chart
Short Meaning: A visual tool used to plan and track project timelines, showing the start and finish dates of tasks.
Longer Explanation: A Gantt chart is a type of bar chart that illustrates a project schedule, showing the start and finish dates of various elements of the project. In the Australian construction industry, Gantt charts are widely used by project managers to plan and monitor progress, identify potential delays, and manage resources effectively. The chart provides a visual representation of the project timeline, making it easier to communicate the schedule to all stakeholders.
How this term is commonly used: โThe project manager used a Gantt chart to track the progress of construction activities and ensure the project stayed on schedule.โ
48. Good Faith
Short Meaning: The obligation to act honestly and fairly in the performance and enforcement of contractual duties.
Longer Explanation: Good faith is an implied duty in Australian contracts, including construction agreements, requiring parties to act honestly and fairly towards each other, without misleading or deceiving. This principle ensures that all parties work collaboratively to fulfil the contractโs objectives, fostering trust and cooperation. Breaching this duty can result in legal disputes### 41. Good FaithShort Meaning: The obligation to act honestly and fairly in the performance and enforcement of contractual duties.
Longer Explanation: Good faith is an implied duty in Australian contracts, including construction agreements, requiring parties to act honestly and fairly towards each other, without misleading or deceiving. This principle ensures that all parties work collaboratively to fulfil the contractโs objectives, fostering trust and cooperation. Breaching this duty can result in legal disputes and claims for damages.
How this term is commonly used: โThe court found that the developer had breached the duty of good faith by withholding critical information during contract negotiations.โ
49. Greenfield Project
Short Meaning: A construction project on undeveloped land, requiring new infrastructure and utilities.
Longer Explanation: A Greenfield project refers to development on previously undeveloped land, typically in a rural or suburban area. In Australia, these projects often involve significant planning and infrastructure development, including roads, utilities, and other essential services. Greenfield projects provide a blank slate for developers but also come with challenges such as environmental assessments, zoning approvals, and infrastructure costs.
How this term is commonly used: โThe Greenfield project required extensive infrastructure development before construction could begin.โ
50. Guaranteed Maximum Price (GMP)
Short Meaning: A contract type where the contractor is reimbursed for costs up to a maximum agreed amount.
Longer Explanation: A Guaranteed Maximum Price (GMP) contract is a type of construction agreement where the contractor is compensated for actual costs incurred plus a fee, but only up to a specified maximum amount. In Australia, GMP contracts are used to provide cost certainty for clients, as they limit the financial exposure on a project. Any costs exceeding the GMP are typically the responsibility of the contractor, unless the client agrees to adjust the contract.
How this term is commonly used: โThe contractor agreed to a GMP contract to provide the client with cost certainty for the high-rise development.โ
51. Head Contract
Short Meaning: The primary contract between the client and the main contractor for the delivery of a construction project.
Longer Explanation: The head contract is the main agreement governing the relationship between the client (or principal) and the main contractor responsible for delivering the project. In Australian construction projects, the head contract outlines the scope of work, payment terms, timelines, and responsibilities of both parties. It serves as the legal framework for the project and is often supported by subcontracts with various trade contractors.
How this term is commonly used: โThe head contract was signed, allowing the contractor to begin mobilising for the construction phase.โ
52. Handover
Short Meaning: The formal process of transferring control of the completed work from the contractor to the client.
Longer Explanation: Handover marks the point at which the contractor officially transfers control of the completed construction project to the client. In Australia, this process typically occurs at practical completion, when the work is deemed sufficiently complete for its intended use. During handover, the contractor provides the client with all necessary documentation, such as as-built drawings, warranties, and operation manuals, and the client inspects the work to confirm it meets the contractual requirements.
How this term is commonly used: โThe handover process was completed, and the client took possession of the new building.โ
53. Hold Point
Short Meaning: A stage in the construction process where work cannot proceed until certain approvals or inspections are completed.
Longer Explanation: A hold point is a specific stage in the construction process at which work must be paused to allow for inspections, tests, or approvals before proceeding. In Australian construction contracts, hold points are critical for ensuring quality and compliance with specifications. They are typically agreed upon in advance and documented in the Inspection and Test Plan (ITP). The work cannot continue until the hold point is released, often by the client or an independent inspector.
How this term is commonly used: โThe project encountered a hold point, requiring an inspection of the foundation work before continuing with construction.โ
54. Implied Terms
Short Meaning: Terms not explicitly stated in the contract but assumed to be included based on the nature of the agreement or legal requirements.
Longer Explanation: Implied terms are provisions that are not expressly written into a contract but are considered to be included based on the law, industry standards, or the conduct of the parties. In Australian construction law, implied terms may relate to aspects such as workmanship, materials, or compliance with building codes. These terms ensure that the contract functions effectively, even if certain details are not explicitly outlined.
How this term is commonly used: โThe court ruled that the implied term of quality workmanship was breached by the contractorโs substandard work.โ
55. Infrastructure Project
Short Meaning: Construction projects involving essential public works such as roads, bridges, and utilities.
Longer Explanation: Infrastructure projects involve the construction of large-scale public works, including transportation systems, utilities, and other critical infrastructure. In Australia, these projects are often funded by government bodies and require comprehensive planning, environmental assessments, and community consultation. Infrastructure projects are essential for supporting economic growth and improving public services, but they often face challenges related to funding, regulatory approvals, and project complexity.
How this term is commonly used: โThe state government announced a new infrastructure project to improve road connectivity in the region.โ
56. Insolvency
Short Meaning: The inability of a company or individual to meet their financial obligations, often leading to liquidation or administration.
Longer Explanation: Insolvency occurs when a company or individual is unable to pay their debts as they fall due. In the Australian construction industry, insolvency can have serious consequences, including the termination of contracts, unpaid subcontractors, and incomplete projects. Insolvent companies may enter into liquidation or administration, where a liquidator or administrator is appointed to manage the companyโs assets and liabilities. The risk of insolvency is a significant concern for all parties involved in construction projects.
How this term is commonly used: โThe builderโs insolvency led to the project being halted, and the subcontractors were left unpaid.โ
57. Integrated Project Delivery (IPD)
Short Meaning: A project delivery method that involves early collaboration between all stakeholders to optimise project outcomes.
Longer Explanation: Integrated Project Delivery (IPD) is a collaborative project delivery approach that involves all stakeholders, including the client, contractors, designers, and suppliers, working together from the early stages of the project. In Australia, IPD aims to optimise project outcomes by fostering collaboration, reducing conflicts, and sharing risks and rewards. This method is particularly effective for complex projects where early involvement and joint decision-making can lead to innovative solutions and improved efficiency.
How this term is commonly used: โThe hospital project used an Integrated Project Delivery approach to ensure that all key stakeholders were involved from the design phase.โ
58. Invitation to Tender (ITT)
Short Meaning: A formal request issued by a client inviting contractors to submit bids for a project.
Longer Explanation: An Invitation to Tender (ITT) is a document issued by a client to potential contractors, inviting them to submit proposals for a construction project. In Australia, the ITT typically includes detailed information about the project scope, contract terms, and submission requirements. Contractors respond with their bids, which are evaluated by the client based on criteria such as price, experience, and capability. The ITT process is a key part of competitive procurement in the construction industry.
How this term is commonly used: โThe client issued an Invitation to Tender for the construction of a new office building, seeking bids from experienced contractors.โ
59. Joint Venture
Short Meaning: A business arrangement where two or more parties collaborate on a specific project, sharing risks and rewards.
Longer Explanation: A joint venture in the construction industry is a partnership between two or more companies or individuals who come together to undertake a specific project. In Australia, joint ventures are common in large-scale or complex construction projects where the parties share the risks, costs, and profits. Each party contributes resources, expertise, and capital, and the joint venture is governed by an agreement that outlines the terms of the collaboration.
How this term is commonly used: โThe two construction firms formed a joint venture to bid on the multi-million-dollar infrastructure project.โ
60. Latent Conditions
Short Meaning: Unforeseen physical conditions encountered during construction that differ from those expected or disclosed.
Longer Explanation: Latent conditions refer to unexpected physical conditions on a construction site that were not apparent during the initial site investigation and differ from those disclosed in the contract documents. In Australia, latent conditions can include unforeseen subsurface conditions, contaminated soil, or hidden structural defects. These conditions often lead to variations in the contract and may result in additional costs and time extensions. Addressing latent conditions properly is crucial to avoiding disputes and ensuring project continuity.
How this term is commonly used: โThe contractor encountered latent conditions, such as unexpected rock formations, which required additional excavation work.โ
61. Latent Defect
Short Meaning: A defect that is not immediately apparent and may not become evident until after the construction work is completed.
Longer Explanation: A latent defect is a flaw or defect in construction work that is not visible or detectable at the time of completion but becomes apparent later. In Australia, latent defects can include issues such as structural weaknesses, faulty materials, or poor workmanship that only become evident after the project is in use. These defects can lead to significant repair costs and may be subject to legal claims against the contractor or builder.
How this term is commonly used: โThe latent defect in the foundation was discovered two years after the building wasHereโs a continuation of the glossary with additional terms and ensuring adherence to your instructions:
62. Latent Defect
Short Meaning: A defect that is not immediately apparent and may not become evident until after the construction work is completed.
Longer Explanation: A latent defect is a flaw or defect in construction work that is not visible or detectable at the time of completion but becomes apparent later. In Australia, latent defects can include issues such as structural weaknesses, faulty materials, or poor workmanship that only become evident after the project is in use. These defects can lead to significant repair costs and may be subject to legal claims against the contractor or builder.
How this term is commonly used: โThe latent defect in the foundation was discovered two years after the building was completed, requiring extensive repairs.โ
63. Latent Defect Insurance (LDI)
Short Meaning: Insurance that covers defects in construction that become apparent after completion and are not visible during standard inspections.
Longer Explanation: Latent Defect Insurance (LDI) provides coverage for structural defects that become apparent after a construction project is completed. In Australia, LDI is particularly important for protecting against defects that were not detectable during inspections and only manifest after the building is in use. This insurance is often required by financiers and is a valuable risk management tool for developers and property owners.
How this term is commonly used: โThe developer secured Latent Defect Insurance to protect against future claims related to hidden construction flaws.โ
64. Lead Time
Short Meaning: The time taken from the initiation of a project or order to its completion or delivery.
Longer Explanation: Lead time in the construction industry refers to the period between the initiation of a process and its completion. This can apply to the time required to procure materials, the time to obtain necessary permits, or the duration from the start of a project to its completion. In Australia, managing lead times effectively is crucial for ensuring that projects stay on schedule, particularly in construction where delays can have significant financial implications.
How this term is commonly used: โThe contractor carefully managed lead times for material orders to ensure that the project remained on schedule.โ
65. Letter of Intent (LOI)
Short Meaning: A document indicating that the client intends to enter into a contract with a contractor, but it is not yet legally binding.
Longer Explanation: A Letter of Intent (LOI) is a preliminary document that outlines the clientโs intention to enter into a formal contract with a contractor. In Australian construction projects, an LOI allows work to commence while the final contract is being negotiated. However, an LOI is not legally binding unless it includes specific terms that both parties have agreed to. It serves as a way to expedite the start of the project while ensuring that the parties are aligned on key terms.
How this term is commonly used: โThe developer issued a Letter of Intent to the contractor, allowing them to begin preparatory work before the final contract was signed.โ
66. Liquidated Damages
Short Meaning: Pre-agreed damages specified in the contract, payable if the contractor fails to complete the project on time.
Longer Explanation: Liquidated damages are a predetermined sum agreed upon in the construction contract, payable by the contractor to the client if the project is not completed by the agreed date. In Australia, liquidated damages are used to compensate the client for losses resulting from delays, such as lost revenue or additional costs. The amount must be a genuine pre-estimate of the clientโs potential losses and not a penalty, as excessive liquidated damages may be unenforceable.
How this term is commonly used: โThe contract included liquidated damages of $5,000 per day for each day the project was delayed beyond the completion date.โ
67. Lump Sum Contract
Short Meaning: A contract where the contractor agrees to complete the project for a fixed price, regardless of actual costs.
Longer Explanation: In a lump sum contract, the contractor commits to completing the construction project for a predetermined, fixed price. This type of contract is widely used in the Australian construction industry because it provides cost certainty for clients. The contractor assumes the risk of cost overruns, meaning that any additional costs incurred beyond the agreed price are the contractor's responsibility unless the client requests changes or additional work. Lump sum contracts are typically used when the project scope is well-defined and unlikely to change.
How this term is commonly used: โThe developer preferred a lump sum contract to avoid unexpected costs during the construction of the new office complex.โ
68. Management of Change (MoC)
Short Meaning: A process for managing changes in a project to ensure they are evaluated, approved, and implemented safely.
Longer Explanation: The Management of Change (MoC) process is a structured approach used in construction projects to manage and document changes to the project scope, design, or execution. In Australia, MoC is critical for ensuring that any proposed changes are thoroughly evaluated for their impact on safety, cost, and schedule before being implemented. This process helps prevent scope creep, ensures that all stakeholders are informed of the changes, and maintains the integrity of the project.
How this term is commonly used: โThe project team followed the Management of Change process to assess the impact of modifying the buildingโs design.โ
69. Material Safety Data Sheet (MSDS)
Short Meaning: A document that provides information on the properties of hazardous chemicals used in the project.
Longer Explanation: A Material Safety Data Sheet (MSDS) is a document that provides detailed information about hazardous chemicals used on a construction site, including their properties, potential health effects, safe handling procedures, and emergency measures. In Australia, it is mandatory for contractors to maintain and provide access to MSDSs for all hazardous materials on site to ensure the safety of workers and compliance with Occupational Health and Safety (OHS) regulations.
How this term is commonly used: โThe contractor provided an MSDS for the chemical sealant used in the project to ensure proper safety protocols were followed.โ
70. Milestone
Short Meaning: A significant point or event in the project timeline, often used to measure progress.
Longer Explanation: Milestones are key points in a construction project timeline that signify the completion of major phases or tasks. In Australia, milestones are often used in contracts to establish payment schedules, project reviews, or deadlines for specific deliverables. Achieving milestones indicates that the project is progressing as planned and provides opportunities for reassessment and adjustments if needed.
How this term is commonly used: โThe projectโs first major milestone was the completion of the buildingโs foundation, which triggered a progress payment.โ
71. Mobilisation
Short Meaning: The process of preparing and deploying resources, personnel, and equipment to start the construction project.
Longer Explanation: Mobilisation refers to the activities undertaken by the contractor to prepare for the commencement of construction work. This includes assembling the workforce, transporting equipment and materials to the site, setting up site facilities, and ensuring that all necessary permits and approvals are in place. In Australia, effective mobilisation is crucial for ensuring that the project starts on time and runs smoothly, as any delays during this phase can impact the entire project schedule.
How this term is commonly used: โThe contractor completed mobilisation ahead of schedule, allowing construction to begin sooner than planned.โ
72. Mobilisation Fee
Short Meaning: A payment made to the contractor at the start of a project to cover initial expenses.
Longer Explanation: A Mobilisation Fee is an upfront payment provided to the contractor to cover the costs associated with starting a construction project. This may include expenses such as setting up the site, transporting equipment, and hiring initial labour. In Australia, mobilisation fees help ensure that the contractor has the necessary resources to begin work promptly and can be particularly important for large or complex projects where significant preparation is required before construction can commence.
How this term is commonly used: โThe client agreed to pay a mobilisation fee to ensure the contractor could quickly set up the site and begin work.โ
73. Non-Conformance Report (NCR)
Short Meaning: A document that records any work that does not meet the required standards or specifications.
Longer Explanation: A Non-Conformance Report (NCR) is a document used to record instances where work on a construction project fails to meet the specified standards, requirements, or contractual obligations. In Australia, NCRs are an important tool for quality control, as they help identify and address issues before they escalate. The report typically details the nature of the non-conformance, its impact on the project, and the corrective actions required to bring the work back into compliance.
How this term is commonly used: โThe project manager issued a Non-Conformance Report after discovering that the installed flooring did not meet the specified standards.โ
74. Notice to Proceed (NTP)
Short Meaning: A formal document authorising the contractor to start work on the project.
Longer Explanation: A Notice to Proceed (NTP) is an official document issued by the client to the contractor, authorising them to begin work on the construction project. In Australia, the NTP marks the start of the projectโs timeline, and all subsequent deadlines and schedules are based on the date the NTP is issued. This document is crucial as it signifies that all pre-construction conditions have been met and that the contractor can mobilise resources and commence work.
How this term is commonly used: โThe contractor received the Notice to Proceed and began mobilisation for the construction of the residential complex.โ
75. Novation
Short Meaning: The replacement of one party in a contract with another, transferring all obligations and benefits to the new party.
Longer Explanation: Novation is the legal process by which one party in a construction contract is replaced by another, with the new party assuming all rights and obligations of the original party. In Australian construction projects, novation often occurs when a contractor is replaced or when a design team is transferred from the client to the main contractor. Novation requires the agreement of all parties involved and is used to ensure continuity and clarity in contractual relationships.
How this term is commonly used: โThe original architect was novated to the main contractor, who took over responsibility for the design and construction phases.โ
76. Occupational Health and Safety (OHS)
Short Meaning: Practices and regulations aimed at ensuring the safety and well-being of workers on a construction site.
Longer Explanation: Occupational Health and Safety (OHS) refers to the policies, procedures, and regulations designed to protect the health and safety of workers in the workplace, including construction sites. In Australia, OHS is governed by state and federal laws, and compliance is mandatory for all employers and contractors. OHS covers a wide range of activities, including risk assessments, safety training, and the use of personal protective equipment (PPE), to minimise the risk of accidents and injuries.
How this term is commonly used: โThe contractor implemented strict OHS protocols to ensure the safety of all workers on the construction site.โ
77. Occupation Certificate (OC)
Short Meaning: A certificate issued by a local authority confirming that a building is safe and suitable for occupation.
Longer Explanation: An Occupation Certificate (OC) is a document issued by a local council or private certifier in Australia, confirming that a building is safe and suitable for occupation. The OC is issued after the final inspection and ensures that the building complies with the Building Code of Australia (BCA) and relevant planning regulations. Without an OC, the building cannot legally be occupied or used for its intended purpose. The OC marks the completion of the construction phase and the beginning of the building's operational life.
How this term is commonly used: โThe builder received the Occupation Certificate, allowing the new office building to be officially occupied.โ
78. Operating and Maintenance Manual (O&M)
Short Meaning: A document that provides instructions for the operation and maintenance of the completed project.
Longer Explanation: An Operating and Maintenance (O&M) manual is a comprehensive guide provided by the contractor at the end of a construction project, detailing the procedures for operating and maintaining the building or infrastructure. In Australia, the O&M manual is an essential document for ensuring that the project continues to function as intended after handover. It typically includes instructions for operating systems, maintenance schedules, warranties, and contact information for suppliers and service providers.
How this term is commonly used: โThe O&M manual was handed over to the client, providing detailed instructions on how to operate and maintain the buildingโs HVAC system.โ
79. Performance Security
Short Meaning: A financial instrument, such as a bond or bank guarantee, used to secure the contractorโs performance under the contract.
Longer Explanation: Performance security in the Australian construction context refers to any financial guarantee, such as a bond or bank guarantee, provided by the contractor to the client to ensure the contractor meets their obligations. This security can be called upon if the contractor fails to perform the work as required by the contract. Performance security provides the client with financial protection and helps to ensure the contractor delivers the project on time and to the agreed quality standards.
How this term is commonly used: โThe client required performance security from the contractor to mitigate the risk of non-performance.โ
80. Prime Cost Item
Short Meaning: An allowance in the contract sum for specific materials or equipment that have not yet been selected by the client.
Longer Explanation: A Prime Cost (PC) item is a provision in a construction contract that allocates a fixed sum for certain materials or equipment that have not been selected at the time of signing the contract. In Australia, PC items are commonly used for fittings, fixtures, or appliances where the exact specifications are undecided. The client later selects the item, and if the actual cost exceeds the PC allowance, the contract sum is adjusted accordingly.
How this term is commonly used: โThe contract included a prime cost item for the kitchen appliances, allowing the client to select the final products during the construction phase.โ
81. Principal Certifying Authority (PCA)
Short Meaning: An individual or organisation responsible for ensuring that building work complies with relevant standards and regulations.
Longer Explanation: In Australia, the Principal Certifying Authority (PCA) is a key figure in the construction process, responsible for overseeing compliance with the Building Code of Australia (BCA) and other relevant regulations. The PCA can be a local council or a private certifier, and their duties include issuing construction certificates, conducting inspections, and ultimately issuing the Occupation Certificate. The PCA ensures that the building work meets all legal requirements, from start to finish.
How this term is commonly used: โThe Principal Certifying Authority conducted regular inspections to ensure that all construction work met the required standards.โ
82. Principal Contractor
Short Meaning: The contractor responsible for coordinating the work of all subcontractors on the project.
Longer Explanation: The principal contractor is the main contractor who takes on the responsibility of managing and coordinating all subcontractors and ensuring that the project is completed according to the contract terms. In Australia, the principal contractor is also responsible for ensuring compliance with health and safety regulations, managing project timelines, and maintaining quality standards. The role of the principal contractor is crucial in large construction projects in Australia, where multiple trades and subcontractors are involved. They act as the central point of contact between the client and the various parties involved in the construction process.
How this term is commonly used: โThe principal contractor coordinated all the subcontractors to ensure the project was completed on time and within budget.โ
83. Provisional Sum
Short Meaning: An estimated amount included in the contract for work that is not fully defined at the time of contracting.
Longer Explanation: A provisional sum is an allowance included in a construction contract for specific work that cannot be precisely defined at the time of signing the contract. In Australia, provisional sums are used when certain aspects of the project, such as site conditions or design elements, are not fully detailed. The provisional sum provides flexibility in the contract, allowing for adjustments based on actual costs incurred once the work is defined and executed.
How this term is commonly used: โThe provisional sum for landscaping was included in the contract, with final costs to be confirmed once the design was completed.โ
84. Public-Private Partnership (PPP)
Short Meaning: A collaborative arrangement between public and private sectors for infrastructure projects.
Longer Explanation: A Public-Private Partnership (PPP) is a funding model for public infrastructure projects, such as roads, hospitals, and schools, where the government collaborates with private sector companies. In Australia, PPPs are used to leverage private sector expertise and investment, sharing the risks and rewards between the public and private partners. These partnerships often involve long-term contracts where the private sector is responsible for designing, building, financing, and operating the infrastructure.
How this term is commonly used: โThe government entered into a PPP to finance and build the new motorway, with the private partner responsible for its operation for 30 years.โ
85. Punch List
Short Meaning: A list of work items identified at the completion of the project that need to be completed or corrected before final payment.
Longer Explanation: A punch list is a document prepared towards the end of a construction project that lists the work that remains to be done or needs to be corrected before the project can be considered complete. In Australia, the punch list is used by the contractor and client to ensure all work meets the contractual standards. The contractor is typically required to address all items on the punch list before final payment is released.
How this term is commonly used: โThe contractor completed all items on the punch list, allowing the client to sign off on the projectโs completion.โ
86. Quality Assurance (QA)
Short Meaning: Procedures and activities aimed at ensuring the quality of the work meets the contract specifications.
Longer Explanation: Quality Assurance (QA) refers to the systematic processes and procedures implemented to ensure that the construction work meets the required standards and specifications. In Australia, QA involves planning, monitoring, and reviewing various aspects of the construction process to prevent defects and ensure compliance with contractual obligations. QA is essential for maintaining high standards of workmanship and for protecting the interests of both the client and the contractor.
How this term is commonly used: โThe contractor implemented a robust Quality Assurance program to ensure that all aspects of the project met the specified standards.โ
87. Quality Control (QC)
Short Meaning: The inspection and testing of materials and workmanship to ensure they comply with the contract requirements.
Longer Explanation: Quality Control (QC) is the process of inspecting and testing materials, workmanship, and construction methods to ensure they meet the specifications outlined in the contract. In Australia, QC is a critical component of construction management, as it helps to identify and rectify issues before they become major problems. QC activities include regular site inspections, material testing, and reviewing construction methods to ensure they align with the required standards.
How this term is commonly used: โThe Quality Control team conducted regular site inspections to ensure that all work met the required standards.โ
88. Quantum Meruit
Short Meaning: A claim for payment based on the value of work performed when no contract exists or where work is done beyond the contract scope.
Longer Explanation: Quantum Meruit is a legal principle that allows a party to claim payment for work performed based on its reasonable value, rather than a pre-agreed contract price. In the Australian construction industry, this claim arises when work is done without a formal contract, or when additional work is performed outside the scope of the existing contract. Quantum Meruit ensures that contractors are fairly compensated for their work, even in the absence of a specific agreement.
How this term is commonly used: โThe contractor filed a Quantum Meruit claim for the additional work completed after the original contract had expired.โ
89. Qualifying Causes of Delay
Short Meaning: Specific events or circumstances outlined in a contract that can justify an extension of time.
Longer Explanation: Qualifying Causes of Delay are events specified in construction contracts that entitle the contractor to an extension of time for completing the project. These causes typically include adverse weather conditions, client-initiated variations, and latent conditions. In Australian Standard Contracts, such as AS 4000, the identification and documentation of qualifying causes are crucial for managing delays without incurring penalties. Properly addressing these causes ensures that both parties understand their rights and obligations regarding project timelines.
How this term is commonly used: โThe contractor submitted a claim for an extension of time due to qualifying causes of delay, including heavy rainfall and unforeseen site conditions.โ
90. Rectification Period
Short Meaning: A period after practical completion during which the contractor must fix any defects at their own cost.
Longer Explanation: The Rectification Period, also known as the Defects Liability Period, is a specific timeframe after practical completion during which the contractor is responsible for rectifying any defects that become apparent. In Australia, this period typically lasts between 6 to 12 months, depending on the contract terms. During this period, the contractor must address any issues raised by the client without additional charge, ensuring that the construction work meets the required standards.
How this term is commonly used: โThe contractor was called back during the Rectification Period to fix a leaking roof discovered after the project was completed.โ
91. Request for Information (RFI)
Short Meaning: A formal request from the contractor to the client or engineer for clarification or additional information about project details.
Longer Explanation: A Request for Information (RFI) is a formal communication tool used in construction projects to seek clarification or additional details on project plans, specifications, or other contractual documents. In Australia, RFIs are essential for addressing ambiguities or discrepancies that may arise during construction. The timely response to RFIs helps prevent delays and ensures that the project progresses smoothly, with all parties having a clear understanding of the requirements.
How this term is commonly used: โThe contractor issued an RFI to clarify the specifications for the electrical wiring in the new building.โ
92. Retention
Short Meaning: A percentage of the contract sum held back by the client to ensure the contractor completes the work satisfactorily.
Longer Explanation: Retention refers to the portion of the contract sum that the client withholds from the contractorโs payments until the project is completed to the client's satisfaction. In Australia, retention is typically used as a form of security to ensure that the contractor addresses any defects or outstanding work after practical completion. The retained amount is usually released in two stages: a portion upon practical completion and the remainder after the defects liability period.
How this term is commonly used: โThe client held a 5% retention from each payment, to be released after the defects liability period.โ
93. Retention Release
Short Meaning: The process of releasing withheld retention funds after the completion of specific milestones or the defects liability period.
Longer Explanation: Retention Release refers to the process of paying out the retention money held by the client once the contractor has met certain project milestones or after the defects liability period. In Australia, the retention amount is usually released in stages, with a portion released upon practical completion and the remainder after all defects have been rectified. This ensures that the contractor fulfills all their obligations before receiving the final payment.
How this term is commonly used: โThe final retention release was issued after the contractor successfully rectified all identified defects.โ
94. Risk Register
Short Meaning: A document that identifies potential risks to the project and outlines strategies to manage them.
Longer Explanation: A Risk Register is a key project management tool used in construction projects to identify, assess, and manage potential risks. In Australia, the Risk Register is an essential part of the projectโs risk management plan, helping to track risks throughout the project lifecycle. It includes details such as the nature of the risk, its potential impact, the likelihood of occurrence, and the mitigation strategies to be implemented. Regular updates to the Risk Register are crucial for proactive risk management.
How this term is commonly used: โThe project manager maintained a detailed Risk Register to monitor and mitigate risks throughout the construction process.โ
95. Scope Creep
Short Meaning: The gradual expansion of the project scope beyond its original objectives, often leading to increased costs and delays.
Longer Explanation: Scope Creep occurs when the scope of a construction project expands beyond the original plans, often without formal approval or adjustments to the contract. In Australia, scope creep is a common issue that can lead to significant cost overruns and delays if not managed properly. Effective project management and clear communication are essential to controlling scope creep, ensuring that any changes to the project are properly documented and approved.
How this term is commonly used: โThe project experienced scope creep when additional features were added without updating the original contract.โ
96. Schedule of Rates
Short Meaning: A list of predetermined prices for specific work items, used for valuing variations in a project.
Longer Explanation: A Schedule of Rates is a document that lists the agreed-upon prices for specific tasks or materials in a construction project. In Australia, it is often used in contracts where the exact scope of work is not fully defined at the outset. The Schedule of Rates allows for flexibility in pricing additional work or variations, as the cost of these items is already predetermined. This method helps streamline the valuation of changes during the construction process.
How this term is commonly used: โThe contract included a Schedule of Rates to facilitate the pricing of any variations during the construction process.โ
97. Schedule of Values
Short Meaning: A document outlining the amount allocated to each work item in a project, used for progress payments.
Longer Explanation: The Schedule of Values is a detailed document that breaks down the total contract sum into individual work items, each assigned a specific value. In Australia, this document is used to facilitate progress payments by assigning a value to each completed task or deliverable. The Schedule of Values helps ensure that payments are made fairly and in proportion to the work completed, providing transparency for both the client and the contractor.
How this term is commonly used: โThe projectโs Schedule of Values was used to determine the amount of each progress payment based on work completed.โ
98. Security of Payment
Short Meaning: Legislation designed to ensure contractors and subcontractors are paid promptly for their work.
Longer Explanation: Security of Payment laws in Australia are designed to protect the cash flow of contractors, subcontractors, and suppliers by ensuring they are paid promptly for work completed. These laws provide a statutory right to claim progress payments, and if necessary, to take action through adjudication to recover unpaid amounts. The legislation varies between states and territories but generally provides a straightforward mechanism for resolving payment disputes without resorting to lengthy legal proceedings.
How this term is commonly used: โThe contractor invoked Security of Payment legislation to recover outstanding payments from the client.โ
99. Serial Defect
Short Meaning: Multiple occurrences of the same defect in the work, indicating a systemic issue.
Longer Explanation: A serial defect refers to the repeated occurrence of the same defect across multiple areas or components of a construction project. In Australia, serial defects are often indicative of a broader issue, such as poor workmanship, substandard materials, or inadequate supervision. Identifying and addressing serial defects early is crucial to prevent widespread problems and ensure the overall quality of the project. Serial defects may lead to significant repair costs and disputes if not properly managed.
How this term is commonly used: โThe presence of serial defects in the cladding installation raised concerns about the overall quality of the construction work.โ
100. Shop Drawings
Short Meaning: Detailed drawings prepared by contractors, suppliers, or fabricators showing how specific portions of the work will be fabricated or installed.
Longer Explanation: Shop drawings are specialized, detailed drawings that illustrate how specific elements of a construction project, such as steel beams, ductwork, or custom-built components, will be fabricated and installed. In Australia, these drawings are typically produced by subcontractors or suppliers and must be reviewed and approved by the projectโs architect or engineer before construction begins. Shop drawings are critical for ensuring that the construction aligns with the design intent and meets all specifications.
How this term is commonly used: โThe contractor submitted shop drawings for the structural steel components, which were reviewed and approved by the engineer.โ
101. Site Conditions
Short Meaning: The physical characteristics of the construction site that can affect the execution of the project.
Longer Explanation: Site conditions encompass all physical aspects of a construction site, including topography, soil quality, weather patterns, existing structures, and environmental factors. In Australian construction contracts, understanding site conditions is crucial for accurate project planning and cost estimation. Site conditions that differ from those anticipated can lead to project delays and additional costs. It is the contractor's responsibility to inspect and account for site conditions during the tendering process.
How this term is commonly used: โThe contractor conducted a thorough assessment of the site conditions to avoid any unforeseen issues during construction.โ
102. Site Instructions
Short Meaning: Directions given by the project manager or engineer to the contractor on how to perform specific tasks during the construction process.
Longer Explanation: Site Instructions are formal directives issued by the project manager, engineer, or architect to the contractor, detailing how specific work should be carried out on a construction site. In Australia, these instructions are typically documented and form part of the project records. They are used to ensure that the construction is completed according to the projectโs design and specifications, and they may involve changes to methods, materials, or sequences of work.
How this term is commonly used: โThe project manager issued a site instruction to modify the drainage layout based on unexpected site conditions.โ
103. Statutory Warranty
Short Meaning: A warranty implied by law that guarantees certain aspects of the construction work, such as quality and durability.
Longer Explanation: In the Australian construction industry, Statutory Warranties are legal guarantees that apply to residential building work, ensuring that the work meets specific standards of quality, durability, and compliance with regulations. These warranties are implied by law and cannot be excluded by contract. Statutory Warranties cover aspectsContinuing from where we left off:
104. Statutory Warranty
Short Meaning: A warranty implied by law that guarantees certain aspects of the construction work, such as quality and durability.
Longer Explanation: In the Australian construction industry, statutory warranties are legal guarantees that apply to residential building work, ensuring that the work meets specific standards of quality, durability, and compliance with regulations. These warranties are implied by law and cannot be excluded by contract. Statutory warranties cover aspects such as structural integrity, water penetration, and proper installation of systems and fixtures. They provide homeowners with protection against defects and poor workmanship.
How this term is commonly used: โThe homeowner relied on the statutory warranty to have the builder rectify a defect in the newly constructed home.โ
105. Subcontractor Agreement
Short Meaning: A contract between the main contractor and a subcontractor outlining the terms of their work on the project.
Longer Explanation: A Subcontractor Agreement is a contract that details the specific terms and conditions under which a subcontractor will perform work for the main contractor on a construction project. In Australia, these agreements are crucial for defining the scope of work, payment terms, timelines, and responsibilities. They ensure that the subcontractorโs work aligns with the requirements of the main contract and provides legal protection for both parties in the event of disputes.
How this term is commonly used: โThe main contractor signed a subcontractor agreement with the electrical contractor to ensure their work complied with the projectโs specifications.โ
106. Superintendent
Short Meaning: A person appointed by the client to oversee the contract and ensure compliance with its terms.
Longer Explanation: In Australian construction contracts, the superintendent plays a crucial role as the clientโs representative, responsible for administering the contract, inspecting the work, and certifying payments. The superintendent has the authority to issue directions, assess variations, and resolve disputes between the client and contractor. Their role is pivotal in ensuring that the project is completed according to the contract terms and to the clientโs satisfaction.
How this term is commonly used: โThe superintendent issued a direction to the contractor to expedite the construction process due to upcoming weather concerns.โ
107. Take-off
Short Meaning: The process of measuring materials and quantities from drawings to prepare a cost estimate.
Longer Explanation: Take-off refers to the detailed measurement of materials and quantities required for a construction project, typically based on architectural and engineering drawings. In Australia, take-offs are used by quantity surveyors or estimators to prepare accurate cost estimates and ensure that all necessary materials are accounted for in the project budget. This process is essential for managing costs and avoiding shortages or overages during construction.
How this term is commonly used: โThe quantity surveyor completed the take-off to ensure that all materials needed for the project were accurately estimated.โ
108. Testing and Commissioning
Short Meaning: The process of verifying that all systems and components are functioning as intended.
Longer Explanation: Testing and commissioning are critical phases at the end of a construction project where all systems, such as electrical, mechanical, and plumbing, are tested to ensure they operate as designed. In Australia, this process ensures that the building is safe, functional, and compliant with relevant standards and regulations before it is handed over to the client. Commissioning also involves training the clientโs operational staff and providing all necessary documentation, such as operation manuals and warranties.
How this term is commonly used: โThe projectโs testing and commissioning phase confirmed that all building systems were functioning correctly before final handover.โ
109. Time and Materials Contract
Short Meaning: A contract type where the contractor is paid for actual time spent and materials used.
Longer Explanation: A Time and Materials (T&M) contract is a flexible agreement where the contractor is paid based on the actual hours worked and materials used on a project, rather than a fixed price. In Australia, T&M contracts are often used when the scope of work is not clearly defined, allowing for adjustments as the project progresses. While this type of contract provides flexibility, it requires close monitoring by the client to ensure costs are kept under control.
How this term is commonly used: โThe client opted for a Time and Materials contract due to the uncertain scope of the renovation project.โ
110. Total Operating Cost (TOC)
Short Meaning: The total cost of operating a building or facility over its lifetime, including maintenance and utilities.
Longer Explanation: Total Operating Cost (TOC) encompasses all expenses associated with running and maintaining a building or facility over its operational life. This includes energy costs, routine maintenance, repairs, and any other operational expenses. In Australia, TOC is an important consideration for building owners and developers, as it provides a comprehensive view of the long-term financial impact of the facility. Effective management of TOC can lead to significant savings and improved sustainability.
How this term is commonly used: โThe developer conducted a TOC analysis to understand the long-term financial implications of the new commercial building.โ
111. Value Engineering
Short Meaning: A systematic approach to improving the value of a project by optimising costs and performance.
Longer Explanation: Value Engineering (VE) is a process used in construction to analyse the functions of a project and identify ways to reduce costs while maintaining or improving performance and quality. In Australia, VE is commonly applied during the design phase to optimise the projectโs value by finding cost-effective alternatives to materials, methods, or designs. The goal of VE is to achieve the best possible outcome for the client within the projectโs budget and time constraints.
How this term is commonly used: โThe project team used Value Engineering to reduce costs without compromising the buildingโs quality or performance.โ
112. Variation
Short Meaning: A change to the scope of work, design, or specifications after the contract has been signed.
Longer Explanation: A variation, also known as a change order, refers to any alteration in the scope of work, materials, design, or other aspects of the construction project after the contract has been agreed upon. In Australia, variations are common and must be documented and approved by both the client and contractor. Variations can impact the projectโs cost and schedule, and they often require adjustments to the contract terms to reflect these changes.
How this term is commonly used: โThe contractor submitted a variation request after the client decided to upgrade the buildingโs facade materials.โ
113. Waiver
Short Meaning: The voluntary relinquishment of a right or claim under the contract.
Longer Explanation: A waiver occurs when a party to a construction contract voluntarily gives up a right or claim, either explicitly or through their actions. In Australia, a waiver can affect the enforceability of certain contract terms, as the party who waives their rights cannot later enforce those rights. Waivers can be temporary or permanent and must be clearly communicated to avoid misunderstandings or disputes.
How this term is commonly used: โThe client issued a waiver, allowing the contractor to complete the project without penalty despite the delay.โ
114. Warranty
Short Meaning: A promise or guarantee provided by the contractor that the work will meet certain standards and be free from defects.
Longer Explanation: In the Australian construction industry, a warranty is a legally binding promise made by the contractor that the completed work will meet specified quality standards and be free from defects for a certain period. Warranties provide assurance to the client that any defects discovered within the warranty period will be rectified at no additional cost. Warranties can cover materials, workmanship, and specific systems, and they are an essential part of the contractual relationship between the client and contractor.
How this term is commonly used: โThe contractor provided a five-year warranty on the roofing materials, ensuring they would be free from defects during that time.โ
115. Work Breakdown Structure (WBS)
Short Meaning: A hierarchical decomposition of a project into smaller, manageable components.
Longer Explanation: A Work Breakdown Structure (WBS) is a project management tool that breaks down a construction project into smaller, more manageable tasks or components. In Australia, the WBS is used to organise and define the total scope of the project, ensuring that all aspects are covered and resources are allocated effectively. The WBS helps project managers track progress, assign responsibilities, and identify potential risks by providing a clear overview of the projectโs structure.
How this term is commonly used: โThe project manager created a detailed Work Breakdown Structure to ensure that all phases of the construction project were clearly defined.โ
116. Work Health and Safety (WHS)
Short Meaning: Regulations and practices aimed at ensuring the safety and well-being of workers on a construction site.
Longer Explanation: Work Health and Safety (WHS) is a set of laws, regulations, and practices in Australia designed to protect workers from health and safety risks in the workplace, including construction sites. WHS regulations mandate risk assessments, safety training, the use of personal protective equipment (PPE), and other measures to minimise the risk of accidents and injuries. Compliance with WHS laws is mandatory, and failure to adhere to these standards can result in severe penalties.
How this term is commonly used: โThe contractor implemented comprehensive WHS protocols to ensure the safety of all workers on the construction site.โ
117. Working Drawings
Short Meaning: Detailed drawings used by contractors and builders to construct a project according to the design.
Longer Explanation: Working drawings are detailed plans used during the construction phase to guide the building process. These drawings include precise dimensions, materials specifications, and other critical information needed to construct the project as designed. In Australia, working drawings are essential for translating the architectโs or engineerโs vision into a physical structure. They are used by contractors, subcontractors, and tradespeople to ensure that all aspects of the construction are executed correctly.
How this term is commonly used: โThe contractor relied on the working drawings to ensure that all structural elements of the building were constructed according to the design.โ
118. Zero Harm
Short Meaning: A safety philosophy aiming for zero incidents, injuries, or harm on construction sites.
Longer Explanation: Zero Harm is a safety initiative adopted by many Australian construction companies, aiming to eliminate all incidents, injuries, and health impacts on construction sites. This philosophy emphasises a proactive approach to safety, with rigorous training, risk management, and safety culture embedded at all levels of theZero Harm
Short Meaning: A safety philosophy aiming for zero incidents, injuries, or harm on construction sites.
Longer Explanation: Zero Harm is a safety initiative adopted by many Australian construction companies, aiming to eliminate all incidents, injuries, and health impacts on construction sites. This philosophy emphasises a proactive approach to safety, with rigorous training, risk management, and safety culture embedded at all levels of the organisation. While achieving absolute zero harm is challenging, the initiative drives continuous improvement and reinforces the importance of safety in the construction industry.
How this term is commonly used: โThe construction company implemented a Zero Harm policy to ensure the highest standards of safety on all their projects.โ
Share with your Network!
Let's chat about how we can help your business
Not quite ready to chat?
Take our free Business Quiz
About the Author
Rachelle Hare
Rachelle Hare is a highly experienced Construction Lawyer and Contract Lawyer, with over 23 years of experience in Tier 1 and Tier 2 Construction Firms, Top Tier Private Practice and Government.
With 23+ years of experience as a Senior Lawyer, Strategic Contracting Adviser and Management Consultant in Construction Law, Contracts, Major Projects, Commercial Advisory, Compliance, Procurement, Contract Management and Risk Management, Rachelle has the rare skills to offer you seamless business advice and legal advice to help support your organisation.
As well as a Lawyer and Business Adviser, Rachelle has also acted as a Strategic Procurement Adviser, Compliance Manager, Strategic Risk Adviser and Commercial Manager.
Rachelle owns Blaze Business & Legal, a combined Commercial Law Firm and Business Advisory Firm located in Brisbane, Queensland, Australia. Blaze Business & Legal assists a broad range of clients in the Construction Industry and related industries, and advises owners, contractors, subcontractors, NFPs and other organisations on a broad range of Construction Law, Commercial Law, Business Advisory and Management Consulting issues in Brisbane, Queensland and around Australia.
Rachelle also owns Blaze Professional Learning, where she offers practical contracting skills, hands-on experience in drafting and working with contracts, and industry insights to help Professionals upskill and advance their careers with real-world skills.
And Rachelle owns Brisbane Livewell Clinic, an Allied Health, Natural Therapies and Wellness Clinic in Wavell Heights and Cannon Hill.